Improved to mostly decision useful for all five audiences, because progress is now stated against the target baseline on the target's own basis, 17.1% above it
This review tests South32's publicly available climate disclosure against CRI's Climate Disclosure Review Rules, which use the CRI Net Zero Standard as the reference for a credible claim together with AASB S2 Climate-related Disclosures. It reflects the information available at the review date, states what the evidence supports, what it does not, and what would resolve each open point, and says "cannot verify", not "no issue", where evidence is missing. It is general information, not legal, financial or investment advice, and not an audit or an assurance engagement. It does not allege illegality, misconduct, greenwashing or dishonesty. Organisations may contact CRI at robc@noco2.com.au to identify an error, provide relevant public information or request review of updated disclosures. See Important information at the end of this report.
| Company | Carbon / supply-chain accounting | Institutional investors | Consumer / retail investors | Consumers & public | Regulators |
|---|---|---|---|---|---|
South32 Limited (S32) | 2 | 2 | 2 | 2 | 2 |
The same disclosure can be reliable for one reader and misleading for another, so we rate decision-usefulness separately for each audience on the three-point scale below. There is no single pass/fail verdict — decision-usefulness is a judgement about each audience, not the report as a whole.
The bar below adds the five audience ratings into an overall score out of 15. It is used only to rank reports against one another — it carries no band and no verdict label. Its colour simply reflects the mix of the five ratings: the more red, the more audiences the disclosure falls short for.
This review assesses whether the company's climate disclosure is *decision-useful*: whether a reader can actually rely on it for the decision they are making. Because a disclosure that is sound for one reader can mislead another, we score decision-usefulness separately for each of the main audiences that rely on climate disclosure. The audiences, and what each needs from the disclosure, are the same across all our reviews:
| Audience | What they rely on the disclosure for |
|---|---|
| Carbon / supply-chain emissions accounting | Lifting the company's emissions figures into their own inventory. They need complete category coverage (nothing material excluded), a single reconcilable footprint, and a disclosed, transparent method. Whether a figure is estimated or supplier-specific is a maturity question, not a fault; the fault is exclusion. |
| Institutional investors | Pricing climate risk (physical and transition) including target credibility and whether targets are being met with real reductions, the completeness of financed / portfolio exposure, and flow-through exposure inherited from investees or counterparties whose own emissions may be growing. They can usually reconstruct detail, so they are judged on whether the true position is derivable. |
| Consumer / retail investors | Understanding the company's climate position and target progress without expert reconstruction. They need the headline claims to match the evidence, the material sources to be targeted, and caveats to be easy to find. |
| Consumers & public | Knowing whether the company's public claims are true: that it is genuinely acting rather than greenwashing, and not fuelling climate change while presenting otherwise. Headline claims matter most to this audience, which is least able to read past a buried caveat. |
| Regulators | Whether the disclosure is compliant, consistent across sources and audiences (does the company say one thing to one audience and something else to another), and useful across the board. |
The overall score is simply the sum of the five audience ratings, out of 15. It has no band and no pass/fail label; we use it only to rank reports against one another; its colour bar reflects the mix of the five ratings (the more red, the more audiences the disclosure falls short for). §2.1 gives each audience's rating and the reason behind it; §1 covers scope and basis, §2.2–2.3 the evidence dashboard, §3 what the disclosure means for a reader (what's counted, financed-emissions detail, real-vs-accounting movement, trajectory), §4 the findings, §5 disclosure-risk, §6 how to fix it and §7 the conclusion; the working annexes show the rule-level derivation.
Two conventions apply throughout. A certification (including the Australian Government's Climate Active program) is treated as a claim to be tested, not as a strength in itself. Detailed disclosure and candour about a company's own gaps are the baseline expected of a credible discloser, not a credit.
| Document | Reviewed? | If missing, effect on this review |
|---|---|---|
| Annual Report 2026 (year ended 30 June 2026), including the Addressing Climate Change section, the statutory sustainability audit and review report, the voluntary limited assurance report, the Remuneration Report and the financial statements | Yes | Primary audited source, and the vehicle for the company's first mandatory climate statements. |
| Climate-related Reporting Methodology 2026 | Yes | Forms part of the statutory Sustainability Report by cross-reference. Carries the FY35 target definition table, the baseline recalculation triggers and the per-category Scope 3 method. |
| Sustainability Databook 2026 (Reporting boundaries, Climate Change, Portfolio, GHG Emissions, Other GHG Emissions, Energy, Emissions Limiting Regulations tabs) | Yes | Source of the five-year series on both portfolio bases, the Scope 3 category tables, the credit retirement register and the Safeguard Mechanism tables. |
| Climate Change Action Plan 2025 | Yes | Stated by the company to constitute the Group's transition plan for AASB S2 purposes. Approved by a 90% vote on a non-binding advisory resolution at the October 2025 annual general meeting. |
| Annual Report 2025, Climate-related Risk and Reporting Methodology 2025 and Sustainability Databook 2025 | Yes | Prior-period comparators for the year-over-year work in section 3.4. |
| NGER register FY2024-25 (Clean Energy Regulator) | Yes | Statutory anchor for the Australian Scope 1, Scope 2 location-based and net energy reconciliation. |
| Sustainability Standards and Frameworks Index 2026 | Not provided | The AASB S2 and TCFD indices were read where reproduced in the Methodology; the SASB and Climate Action 100+ mapping was read only where reproduced in the Annual Report. Framework-alignment findings are limited accordingly. |
| Climate Change Action Plan 2022 | Not provided | The 2022 commitments are assessed from the way the 2025 plan restates them. |
| Standard / framework | Referenced by company? | How strongly | Sector module(s) applied |
|---|---|---|---|
| Corporations Act / Ch 2M | Yes: as the basis of both the financial report and the climate statements | Binding | Mining and metals |
| AASB S2 | Yes | Binding: for the first time. Climate statements prepared under sections 296A, 296C and 296D, with a Directors' declaration, an unmodified statutory audit opinion over Scope 1 and Scope 2 and an unmodified review conclusion over governance and strategy. Transitional reliefs applied for comparatives and Scope 3; the December 2025 amendments early adopted | Mining and metals |
| ASIC RG 280 | No | Not referenced: engaged in substance, since the sustainability report is now prepared under the mandatory regime | Mining and metals |
| GHG Protocol (Corporate / Scope 2 / Scope 3) | Yes | In accordance with: prepared in accordance with, and named as the reporting criteria for the voluntary Scope 3 assurance. One stated departure: biogenic CO₂ is included inside Scope 1 rather than reported separately | Mining and metals |
| PCAF (financed emissions) | No | Not applicable: not a financial institution | Not applied |
| SBTi | Yes: expressly to state that the FY35 target has not been third-party validated | Mentioned: referenced, not applied | Mining and metals |
| Climate Active / other carbon-neutral framework | No | Not applicable: no carbon-neutral or net-zero-achieved claim is made for the period | Not applied |
| Certificates (GreenPower / LGC / ACCU / REC) | Yes | With reference to: Australian Carbon Credit Units and South African offset units are disclosed as retired for regulatory compliance, and are stated to be excluded from the net emissions calculation | Mining and metals |
| TCFD | Yes | With reference to: "consistent with" (consistency asserted) | Mining and metals |
| ICMM Principles and Performance Expectations | Yes | With reference to: "informed by" | Mining and metals |
| GRI | Yes | With reference to: "informed by" | Mining and metals |
| TNFD | Yes | With reference to: "informed by" | Mining and metals |
| Climate Action 100+ Net Zero Standard for Diversified Mining | Yes | With reference to: "informed by" | Mining and metals |
| SASB | Yes | With reference to: "informed by" | Mining and metals |
| Sea Cargo Charter | Yes | With reference to: "informed by" | Mining and metals |
This is a standard review of South32's FY2026 climate disclosure, run on the FY2026 reporting suite and the four earlier years of data that suite carries, with the FY2025 suite read as the prior-period comparator. FY2026 is South32's first mandatory reporting year under AASB S2.
Three limitations bound the conclusions. The Sustainability Standards and Frameworks Index 2026 was not provided, so the company's framework mapping was tested only where the Annual Report and the Methodology reproduce it. The 2022 Climate Change Action Plan was not provided. And the FY2026 National Greenhouse and Energy Reporting submission period was still open at the reporting date, so the FY2026 statutory register position cannot be reconciled; the FY2025 register position can be and is.
One event after the balance date shapes almost everything in this report and is treated as the company presents it: on 1 July 2026 South32 announced a binding conditional agreement to sell its aluminium value chain assets, excluding Mozal Aluminium, to Alcoa. The disclosure is prepared on the portfolio as at 30 June 2026 and does not reflect that transaction. Where the transaction bears on a finding, the review says so and uses only figures the company itself publishes about it.
Where a figure is disclosed but its derivation is not shown, the review records it as unverified rather than as an error. Where a driver of a movement is named but not sized, the review says so and does not substitute its own estimate.
What the company should fix first: state FY2026 progress on one basis, the continuing-operations basis the audit and the target both use, and publish the residual portfolio's FY2026 emissions beside the 1.7 MtCO₂e pro-forma baseline so a reader can see where the target starts and stands after the sale.
| Dimension | Rating | Justification |
|---|---|---|
| Headline claim ↔ evidence match | 3/5 | The headline figure now carries its position against the target baseline in the same sentence. It is stated on a portfolio basis the baseline does not use, which overstates the shortfall by 1.7 percentage points. |
| Disclosure quality | 10 / 15 overall | Asset-level, source-level and gas-level inventory across five years, dual Scope 2 bases, dual portfolio definitions, an organisational boundaries table, and a methodology document stating inputs, assumptions, exclusions and factor sources for every category. |
| Inventory completeness (Scope 1/2/3) | 4/5 | Nine of fifteen Scope 3 categories quantified or folded, four not applicable, two excluded on a stated materiality basis. One unsized commodity exclusion inside processing of sold products and an acknowledged but unquantified double count between categories. |
| Financed-emissions completeness (if FI) | N/A | Not a financial institution. |
| Target credibility | 1/5 | Above the baseline in year five of fourteen, no interim target, and a baseline the announced sale would cut by about 90% with the consequences not yet assessed. |
| Real reduction vs accounting movement | 2/5 | The 1.0% fall is a divestment and a smelter closure offset by an electricity emission factor; the identified abatement is about 0.1 MtCO₂e. The company names the drivers, which is the improvement. |
| Offset / certificate / renewable integrity | 5/5 | Credits retired are itemised by project, vintage, registry and facility, none is applied to the net figure, and the gross target is stated to equal the net target. |
| Assurance coverage vs claim | 4/5 | Reasonable assurance over Scope 1 and both Scope 2 bases on continuing operations; limited assurance over Scope 3 and total energy. Emissions intensity, assured last year, is no longer in scope, and the comparatives are expressly outside the audit. |
| Standards / compliance confidence | 5/5 | First mandatory year delivered with a Directors' declaration, unmodified opinion and conclusion, disclosed transitional reliefs and early adoption of the December 2025 amendments. |
| Comparability (like-for-like only) | 3/5 | The continuing series is consistently re-based and the Scope 3 restatement is quantified. Against that, biogenic CO₂ moved inside Scope 1 without restatement, and FY2021, the baseline year, has dropped out of every published series. |
| Reader accessibility | 3/5 | The position against the baseline is where the reader lands. The chart beside it is on the other portfolio basis and starts after the baseline year. |
| Evidence limitations | 3/5 | The standards index was not provided; the FY2026 register position is not yet published; several derivations are stated without being shown. |
| Area | Rating | Basis |
|---|---|---|
| Corporations Act / Ch 2M | No apparent issue | Unqualified audit opinion on the financial report, which carries a climate-related risks and opportunities note covering base-case warming assumptions, portfolio resilience, carbon pricing, decarbonisation capital treatment and physical impacts. |
| AASB S2 | Appears broadly compliant: minor limitations | First mandatory year. Directors' declaration under sections 296C and 296D; unmodified audit opinion over Scope 1 and both Scope 2 bases; unmodified review conclusion over governance and strategy. Transitional reliefs applied and disclosed: no comparatives except where voluntarily presented, and Scope 3 disclosed voluntarily and not prepared in accordance with the standard. Quantified anticipated financial effects are withheld on a stated measurement-uncertainty ground. |
| ASIC RG 280 | Appears broadly compliant: minor limitations | The guidance is engaged now that the sustainability report is prepared under the mandatory regime. The disclosure is not framed against it, and the progress statement mixes portfolio bases. |
| GHG Protocol / Scope 2 / Scope 3 | Appears broadly compliant: minor limitations | Corporate Standard, Scope 2 Guidance and Scope 3 Standard named as the reporting criteria; dual Scope 2 reporting applied. One stated departure: biogenic CO₂ of 0.09 MtCO₂e is included inside Scope 1 rather than reported separately, on the company's reading of AASB S2, with prior years not restated. |
| PCAF / financed emissions | Not applicable for the period | Not a financial institution. |
| Carbon-neutral / net-zero framework | No apparent issue | No carbon-neutral or net-zero-achieved claim is made. The 2050 net zero position is described by the company as a goal, defined as an outcome for which no delivery pathway has been identified. |
| Certificates / credits | No apparent issue | 79,981 Australian Carbon Credit Units and 100,846 South African offset units retired, itemised by project, vintage, registry and facility, all against regulatory liabilities, and none included in the net emissions calculation. |
| Other company-referenced framework | Cannot verify: evidence not provided | TCFD consistency is asserted and indexed in the Sustainability Standards and Frameworks Index 2026, which was not provided. |
FY2026 (year ended 30 June 2026), operational control boundary, total operations basis, which is the basis the narrative headline and the Scope 3 category commentary are stated on and which includes operations divested during the year. The figures carrying the statutory audit opinion are the continuing operations figures: Scope 1 5.9, Scope 2 market-based 14.3 and Scope 2 location-based 14.4 MtCO₂e, for totals of 20.2 and 20.3. Both series appear in §3.4 and Annex K, where the basis is a column heading. All figures in MtCO₂e as reported.
| Scope / category | Status | Quantified (MtCO₂e) | Material? | Note |
|---|---|---|---|---|
| Scope 1: combustion / fugitive / process | Reported | 6.2 | Yes: 30% of Scope 1 and 2 | Broken out by source (coal and coke 3.6, natural gas 1.8, distillate and gas 0.4, fugitive 0.2, other 0.1), by gas and by operation. Includes 0.09 MtCO₂e of biogenic CO₂ for the first time. Reasonable assurance on the continuing-operations figure. |
| Scope 2: electricity (location-based) | Reported | 14.5 | Yes | Scope 1 and 2 location-based total 20.7 MtCO₂e. Not additive with the row below: the two rows measure the same electricity. |
| Scope 2: electricity (market-based) | Reported | 14.4 | Yes: the basis the FY35 target is measured on | Scope 1 and 2 market-based total 20.5 MtCO₂e, the headline figure. The gap to location-based has closed from 4.0 MtCO₂e to 0.1; the cause is in §3.3. |
| Scope 3 C1 Purchased goods & services | Reported | 2.8 | Yes: 10% of Scope 3 | Split into high-emission purchased goods 1.3 and other 1.6. Supplier-specific, average-data and spend-based methods by data availability. |
| Scope 3 C2 Capital goods | Reported within C1 | Included in the 2.8 above | Yes | Reported inside Category 1 because the spend data used for Category 1 already captures capital goods. |
| Scope 3 C3 Fuel- & energy-related | Reported | 1.5 | Yes | |
| Scope 3 C4 Upstream transport & distribution | Reported | 0.9 | Yes | Rose on higher shipment volumes from Australia Manganese. Includes third-party transport of the company's share of non-operated joint venture production. |
| Scope 3 C5 Waste | Excluded | Not measured | No: on the company's stated assessment | Assessed as not material; waste-related utility spend is stated to be captured in Category 1. Basis is an assertion, not a bounding estimate. |
| Scope 3 C6 Business travel | Reported | 0.0 | No | Below 0.05 MtCO₂e (reported as 0.0) |
| Scope 3 C7 Employee commuting | Reported | 0.0 | No | Below 0.05 MtCO₂e (reported as 0.0) |
| Scope 3 C8 Upstream leased assets | Reported within Scope 1 | Included in the 6.2 above | No | Under the operational control approach, leased assets the company controls sit in Scope 1. |
| Scope 3 C9 Downstream transport & distribution | Reported | 0.1 | No | Fell on fewer free-on-board shipments. |
| Scope 3 C10 Processing of sold products | Partial | 21.8 | Yes: 76% of Scope 3 and the largest single line in the whole footprint | Manganese 10.8, alumina 9.6, aluminium 1.1, copper 0.3. Rose 50% on higher alumina sales and the restart of Australia Manganese. Downstream processing of zinc and lead concentrates, molybdenum, gold and silver is excluded on a stated but unquantified materiality basis. |
| Scope 3 C11 Use of sold products | Not relevant | Not applicable | No | The company states it no longer produces products in this category following the August 2024 sale of Illawarra Metallurgical Coal. Was 1.5 MtCO₂e in FY2025. |
| Scope 3 C12 End-of-life of sold products | Excluded | Not measured | No: on the company's stated assessment | Assessed as not material on the ground that the products are metals and minerals with minimal end-of-life emissions. Basis is an assertion, not a bounding estimate. |
| Scope 3 C13 Downstream leased assets | Not relevant | Not applicable | No | No downstream leased assets. |
| Scope 3 C14 Franchises | Not relevant | Not applicable | No | No franchised operations. |
| Scope 3 C15 Investments / financed & facilitated | Reported | 1.4 | Yes | Equity share of Scope 1 and 2 from non-operated joint ventures: Brazil Alumina 59%, Brazil Aluminium 27% and Sierra Gorda 14% of the category. Outside the reasonable assurance opinion, which is disclosed. |
N/A: not a financial institution.
| Reported change | Driver | Real-world reduction? |
|---|---|---|
| Scope 1 and 2, total operations basis: 20.7 MtCO₂e in FY2025 to 20.5 in FY2026, a fall of 1.0% | Mixed: two large movements in opposite directions. Scope 1 fell 1.25 MtCO₂e, which the company attributes to the divestment of Cerro Matoso and the placing of Mozal Aluminium on care and maintenance. Scope 2 market-based rose 1.06 MtCO₂e on higher Eskom-supplied electricity at Mozal and a higher Eskom emission factor. | No: the fall is portfolio change net of a grid emission factor. Identified abatement is about 0.1 MtCO₂e at Worsley Alumina. |
| Scope 1 and 2, continuing operations basis (the basis the audit and the FY35 target both use): 19.3 MtCO₂e in FY2025 to 20.2 in FY2026, a rise of 4.7% | Mixed: composition of the retained portfolio and the Eskom emission factor. | Increase |
| Scope 1 and 2 against the FY2021 target baseline: 17.5 MtCO₂e adjusted baseline against 20.5 reported, which the company states as 17.1% above | Mixed: southern African drought across FY2025 and FY2026, reducing hydroelectric supply to Mozal Aluminium and increasing reliance on coal-fired Eskom electricity, on the company's own account. | Increase: the position is above the starting point. |
| Scope 2 location-based, total operations: 17.3 MtCO₂e in FY2025 to 14.5 in FY2026, a fall of 16.2%, in the same year the market-based figure rose 8.0% | Mixed: two measures of the same electricity moving in opposite directions. The company narrates only the market-based rise. The location-based fall follows the annual update of the South African grid emission factor source together with the reduction in consumption at Mozal, and the disclosure does not separate them. | Cannot verify: the consumption element is real and the factor element is not, and the split is not given. |
| Mozal Aluminium: energy consumption fell 31% to 26.9 PJ while its emissions rose 8% to 3.9 MtCO₂e | Mixed: the electricity source changed. Hydroelectric supply was replaced by predominantly coal-fired Eskom electricity before the smelter was placed on care and maintenance in March 2026. | Increase: less energy, more emissions, because of what generated the energy. |
| Renewable share of energy consumption: 16% in FY2025 to 9% in FY2026 (25 PJ to 12.5 PJ) | Mixed: physical. The loss of Cahora Bassa hydroelectric supply to Mozal Aluminium and the divestment of Cerro Matoso, partly offset by biomass consumption at Worsley Alumina nearly doubling. | No: at group level. The Worsley biomass increase is real and is the year's clearest abatement. |
| Scope 3, total operations: 23.5 MtCO₂e in FY2025 to 28.6 in FY2026, a rise of 22% | Activity: volume. Processing of sold products rose 50% on higher alumina sales and the restart of Australia Manganese after the FY2024 cyclone damage, partly offset by lower purchased goods and services following the Cerro Matoso divestment and the Mozal suspension. | Increase: a volume-driven one. Prior-year comparability is preserved because the method did not change. |
| Scope 1: 7.4 MtCO₂e in FY2025 to 6.2 in FY2026, a fall of 16.9% | Mixed: divested operations contributed 0.9 MtCO₂e of the fall and Mozal Aluminium 0.4; Worsley Alumina's biomass substitution and lower coal use contributed about 0.1; increases at Australia Manganese and the Hermosa project, and 0.09 MtCO₂e of biogenic CO₂ now counted inside Scope 1, offset part of it. | Partly: only the Worsley element, about 0.1 MtCO₂e. |
The year does not decompose into a reduction. The reported movement is a 1.0% fall composed of a 1.25 MtCO₂e portfolio and closure effect set against a 1.06 MtCO₂e increase from an electricity emission factor, so no meaningful share of it is own action. That is why no decomposition chart is drawn: the arithmetic of the year is two offsetting movements, not a reduction with drivers.
Five years of data are published for every headline series on two portfolio definitions, and the FY2026 suite adds a five-year Scope 3 category table on the continuing basis, which did not exist before. On the basis the target is measured and the audit covers, the direction is upward: operational emissions at the operations South32 still holds were 17.9 MtCO₂e in FY2022 and 20.2 in FY2026, and they rose 4.7% in the reviewed year. On the basis the company charts, they are close to flat, running 22.0, 21.7, 20.3, 20.7 and 20.5. The company states the position against the target baseline in words on the same page, which it did not do a year ago; the chart beside that sentence is still drawn on the other basis, and it now begins in FY2022, so the FY2021 baseline year has dropped out of every published series.
Value-chain emissions moved the other way from the prior year and for a straightforward reason. Scope 3 rose from 23.5 to 28.6 MtCO₂e on the total operations basis and from 21.6 to 28.5 on the continuing basis, driven by processing of sold products rising 50% as alumina sales increased and Australia Manganese returned to production. The prior year's figure was restated upward from 22.7 to 23.5 following what the company describes as a third-party calculation error, with the affected categories named and quantified.
Two structural changes bound the series. Mozal Aluminium, 19% of operational emissions, was placed on care and maintenance on 15 March 2026 after failing to secure an affordable long-term electricity supply; the company states that this did not trigger a baseline recalculation because the smelter remains under its operational control. Cerro Matoso was divested on 1 December 2025 and the FY2021 baseline was adjusted to 17.5 MtCO₂e accordingly. Separately, the announced sale of the aluminium value chain would, on the company's own figure, reduce that FY2021 baseline to about 1.7 MtCO₂e.
Metrics over time
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 | Movement | Driver | Note |
|---|---|---|---|---|---|---|---|---|
| Scope 1 (MtCO₂e) | 10.1 | 10.3 | 9.4 | 7.4 | 6.2 | Down: 38.6% since FY2022 | Boundary or M&A: divestment and the Mozal suspension account for 1.3 of the 1.2 MtCO₂e net fall in the reviewed year | Total operations. Continuing basis: 6.6 to 5.9, down 10.6%. Includes 0.09 MtCO₂e of biogenic CO₂ from FY2026, excluded in prior years |
| Scope 2 location-based (MtCO₂e) | 20.7 | 19.7 | 18.0 | 17.3 | 14.5 | Down: 29.9% since FY2022 | Mixed: portfolio, consumption and grid emission factors, not separated | Total operations. Continuing basis: 20.1 to 14.4. The FY2026 fall of 16.2% is not narrated anywhere in the disclosure |
| Scope 2 market-based (MtCO₂e) | 11.9 | 11.4 | 10.9 | 13.3 | 14.4 | Up: 21.0% since FY2022 | Mixed: physical supply and the Eskom emission factor | Total operations. Continuing basis: 11.3 to 14.3, up 26.5%. The gap to location-based has closed from 8.8 MtCO₂e in FY2022 to 0.1 in FY2026 |
| Scope 3 total (MtCO₂e) | 67.4 | 65.0 | 54.2 | 23.5 | 28.6 | Down: 57.6% overall, up 21.7% in the reviewed year | Mixed: portfolio and method to FY2025; volume in FY2026 | Total operations, by category in Annex K. FY2025 restated from 22.7 to 23.5 on a stated third-party calculation error, with Categories 1 and 4 quantified. Continuing basis: 47.3 to 28.5 |
| Emissions intensity (tCO₂e per tonne copper-equivalent) | Not disclosed | 20.4 | 20.6 | 24.3 | 25.9 | Up: 26.9% since FY2023 | Activity: emissions broadly flat, production mix changed | Earlier years revised to FY2025 realised prices, which is disclosed. Dropped from the assurance scope in FY2026, having been assured in FY2025 |
| Renewable electricity (% of consumption) | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not applicable | South32 publishes a renewable share of energy rather than of electricity (row below). No certificate-based renewable claim is made |
| Certificates and offsets retired (tCO₂e) | Not disclosed | Not disclosed | Not disclosed | 0 | 0 | Flat: none applied to the net figure in either year | Not applicable | Net equals gross in both years; compliance retirements are in the rows below |
| Total Scope 1 and 2 market-based, continuing operations (MtCO₂e) | 17.9 | 17.7 | 17.0 | 19.3 | 20.2 | Up: 12.8% since FY2022 | Mixed: portfolio composition and the Eskom emission factor | The basis the FY35 target and the audit use. The FY2021 baseline of 17.5 MtCO₂e is no longer carried in this series |
| Renewable share of energy (%) | 20% | 21% | 19% | 16% | 9% | Down: from 20% to 9% | Mixed: loss of hydroelectric supply to Mozal Aluminium and the Cerro Matoso divestment, partly offset by biomass at Worsley Alumina | Renewable energy 33 PJ in FY2022 to 12.5 PJ in FY2026 |
| Australian Carbon Credit Units retired for compliance (units) | Not disclosed | Not disclosed | Not disclosed | 79,185 | 79,981 | Flat: 79,185 to 79,981 | Not applicable | Compliance retirements only; none applied to the net emissions figure |
| South African offset units retired for compliance (units) | Not disclosed | Not disclosed | Not disclosed | 52,875 | 100,846 | Up: 52,875 to 100,846 | Not applicable | As above |
Targets and claims over time
| Target or claim | As first stated (period) | As stated for FY2026 | Change | Explained? | Note |
|---|---|---|---|---|---|
| FY35 operational emissions target | Halve operational emissions by FY2035 from FY2021, covering 100% of operational emissions (FY2021) | "Net, 50%. Gross, 50% (no current planned use of carbon credits)"; adjusted baseline 17.5 MtCO₂e | Strengthened; Rebased: gross target stated equal to the net target, after the FY2025 net description; baseline adjusted for the Cerro Matoso divestment | Yes: the company states neither pathway was expected to require voluntary carbon credits | The company states the announced sale would reduce the FY2021 baseline to about 1.7 MtCO₂e and that it will reassess the target in FY2027 (F-5). No interim target in either year (F-8) |
| Net zero by 2050 goal | Net zero operational emissions by 2050, set as a goal (FY2016) | Unchanged, and the company states it plans to review the 2050 pathway in light of the sale | Extended: to all scopes in FY2023 | Cannot verify: the FY2023 change was not reviewed at source | The company's own definitions distinguish a "target", which has an identified pathway, from a "goal", which does not |
| Value-chain engagement objectives | Engage 80% of key suppliers and 80% of key customers by FY2028 (FY2025) | Reported achieved at over 80% for suppliers and over 90% for customers | Achieved: two years early, on denominators that are not published | Not applicable | Value-chain emissions rose 22% in the same year (F-9) |
Safeguard Mechanism position (Australian facilities). FY2023: all three within baseline. FY2024: two of three exceeded. FY2025 (published in FY2026): all three exceeded, by 183,312 tCO₂e combined. Deteriorating; regulatory. 79,981 Australian Carbon Credit Units were surrendered in FY2026 against those excess emissions. How the balance was acquitted is not stated.
Assurance scope. FY2025: reasonable assurance over total-operations Scope 1 and 2 on both bases; limited over Scope 3, energy and intensity. FY2026: statutory reasonable assurance over continuing-operations Scope 1 and both Scope 2 bases; limited over Scope 3 and energy. Deepened in status, narrowed in content. Emissions intensity left the assured set. Comparatives are expressly outside the audit engagement.
The principal exposure is the gap between a commitment presented as live and a commitment whose measurement basis is about to change by an order of magnitude. The disclosure describes a target to halve operational emissions from 17.5 MtCO₂e, discloses that the announced sale would reduce that starting point to about 1.7 MtCO₂e, and says the implications will be assessed next year. Between those two facts sits a reader who cannot tell what the commitment will mean. What limits the exposure is that all three statements appear within four pages of one another, and that the company states its position against the baseline in the first sentence of the emissions section rather than leaving it to be reconstructed. The secondary exposure is arithmetic: the number the company measures itself against is built from two different portfolio definitions, and the number the auditor signed is a third.
| Lens | Exposure | Confidence | What drives it | What would reduce it |
|---|---|---|---|---|
| Legal (misleading-conduct / disclosure / director-duty) | Low to moderate | Medium to high | The target is presented unqualified in the plan-at-a-glance graphic while the pages either side disclose the sale, the pro-forma baseline and the pending review (F-5). Each component is accurate and co-located, which materially limits the exposure. The progress statement mixes portfolio bases, though in the direction unfavourable to the company (F-6). | Presenting the target with its pending recalibration attached wherever it appears, and stating progress on one basis. |
| Regulatory (ASIC / ACCC / Clean Energy Regulator / AASB S2) | Moderate | High | The first mandatory climate statements are delivered with a Directors' declaration and unmodified opinions, which is the substantial mitigant. Against that, the narrated figures sit outside the audit scope (F-12), a statutory document carries unresolved placeholders (F-17), and all three Australian Safeguard facilities exceeded their FY2025 baselines with the acquittal unreconciled (F-13). | Narrating the audited figures, closing the placeholder defect, and publishing a facility-level Safeguard acquittal. |
| Technology (dependence on unproven abatement) | High | High | The alumina pathway rests on steam electrification and low-carbon calcination, and the completed first-phase study found a technically feasible route defeated for now by capital intensity and electricity market conditions. A second study, waste heat to digestion, was assessed and abandoned. The aluminium pathway rests on an electricity solution in South Africa that has not been found (F-21). | Quantified, dated pathway steps with disclosed capital, and a stated fallback for each. |
| Physical (physical-risk disclosure consistency) | Moderate | High | Physical risk is assessed at asset level on downscaled CMIP6 data under two scenarios and carried into life-of-operation plans, valuations and closure provisions, consistently across documents. The exposure is realised rather than theoretical: a Southern African drought is the company's own stated explanation for being 17.1% above its target baseline, and a cyclone removed and then restored a fifth of value-chain emissions across two years. The disclosure treats the emissions consequence as an external factor rather than as a quantified physical risk to the target. | Linking the physical-risk assessment to target delivery, and stating the emissions sensitivity of the target to hydrological supply. |
| Other: commercial | High | High | The two operations carrying 76% of operational emissions are under a binding conditional agreement to be sold, a third carrying 19% is on care and maintenance with no stated future, and the target, the transition plan, the 2050 goal and the decarbonisation pathways are all stated to be under review as a result (F-5). Almost nothing in the climate architecture survives the transaction unchanged. | Publishing the residual portfolio's position and the intended treatment of the target before the transaction completes. |
| Claim / metric | To the regulator | To investors / public | Consistent after normalising boundary? |
|---|---|---|---|
| Australian Scope 1 emissions | 3,476,916 tCO₂e reported to the National Greenhouse and Energy Reporting register for FY2024-25 | Safeguard covered Scope 1 emissions for the same year total 3,476,855 tCO₂e across Worsley Alumina, Groote Eylandt and Cannington | Yes: the residual is 61 tonnes on 3.48 million. |
| Australian net energy | 52,156,288 GJ, or 52.2 PJ, to the same register | Australian operations' energy use disclosed at 52.3 PJ for FY2025 across the same three operations | Yes: for the reconcilable year. |
| FY2026 operational emissions | The audited figures under section 296C are Scope 1 of 5.9 and Scope 2 of 14.3 market-based and 14.4 location-based, continuing operations | The narrated figure is 20.5 MtCO₂e, being the total-operations market-based total, which the audit does not cover | Yes: reconcilable, and both bases are tabulated. The divergence is that the audited figures are not the narrated ones and the page does not say so. |
| Progress against the FY35 target | Not stated to a regulator for the period | "17.1% above the FY21 baseline of 17.5 Mt CO2-e", computed from a total-operations performance figure against a continuing-operations adjusted baseline | No: on its own terms. The company's boundaries table states that continuing-operations information is presented against continuing-operations baseline years. |
| The FY35 target's character | The financial statements describe the target as "halve its net operational emissions by FY35 from FY21 levels" | The methodology states "Net, 50%. Gross, 50% (no current planned use of carbon credits)"; the plan-at-a-glance states "Halve our net operational emissions by FY35 from FY21 levels" | Yes: one description across the statutory report, the methodology and the plan. |
| Scope 2 movement | Not stated to a regulator for the period | "Scope 2 emissions increased 8% (1.1 Mt CO2-e) from FY25", basis unnamed, on a page whose table shows location-based Scope 2 falling 16% | Yes: reconcilable from the table, but the narrated sentence and the tabulated series tell opposite stories to a reader who does not check the basis. |
| Finding | Review finding (why it matters) | NoCO2 mechanism | Document / clause | Required evidence | Likely NoCO2 outcome |
|---|---|---|---|---|---|
| F-5 the target baseline would fall about 90% on completion of the announced sale | A commitment to halve emissions becomes a commitment to halve a tenth of them, and no position for the residual portfolio is published | Reduction obligations restated on structural change, with the obligation carried through the portfolio change rather than suspended | 4.4 Organisational Boundary; 4.7 Reduction Obligations; 5.1.10 Emissions Tracking (restatement transparency) | The pro-forma current position beside the pro-forma baseline, and a stated treatment of the obligation on completion | Non-conformance while the obligation is neither restated nor stated to be withdrawn |
| F-6 progress is stated across two portfolio definitions | The most important number in the disclosure cannot be reproduced as printed on matching definitions | Emissions tracking presented on the basis the reduction obligation is measured on | 5.1.10 Emissions Tracking; 5.1.11 Reduction Obligation Progress | The performance year and the baseline year on one stated basis | Non-conformance on progress presentation until the tracking basis and the obligation basis are the same |
| F-7 the residual reduction required is not stated | Target feasibility cannot be assessed without the residual and the implied annual rate | Reduction obligation progress against a defined trajectory | 4.7 Reduction Obligations; 5.1.11 Reduction Obligation Progress | Residual reduction required and the annual rate, restated each period | Conformance achievable: the inputs are published and assured |
| F-8 no interim target | Nine years with no testable milestone, against an endpoint that is itself under review | A dated reduction trajectory with interim points | 4.7.4 Accelerated Reduction Timeline; 4.9.2 Metrics & Targets | A dated interim milestone with expected abatement | Non-conformance until an interim point exists |
| F-9 value-chain emissions carry no reduction target and rose 22% | More than half the footprint sits outside every measurable commitment, and the commitments that exist are engagement counts | Influence Based Inventory with defined obligations over non-attributable emissions | 4.5.6 Influence Based Inventory; Annex B; 4.7 Reduction Obligations | A quantified objective over processing of sold products, or a stated influence tonnage and date | Non-conformance on value-chain obligations; the engagement programme is an input, not an obligation |
| F-10 decarbonisation expenditure of US$3.4 million against US$1,441 million of capital expenditure | The capital signal cannot be reconciled with a commitment requiring about 8.9% a year | Required Interventions Schedule with costed, scheduled interventions | 4.7.1 Required Interventions; 4.7.2 Clean Alternative Assessment | Each intervention with expected abatement, capital and date; each rejected option with its ground of rejection | Non-conformance until interventions are scheduled and costed |
| F-11 the location-based Scope 2 fall is unexplained | A grid emission factor update can be read as abatement | Methodology disclosure for market and location-based Scope 2, with movement attribution | 4.5.5 Methodology, market versus location-based; 5.1.13 Contractual Instruments for Purchased Energy | The tonnage attributable to consumption and to the factor change | Non-conformance on movement attribution |
| F-12 the audited figures are not the narrated figures | Reasonable assurance attaches to numbers the reader mostly does not meet | Assurance scope aligned to the reported claim | 6.1 Assurance; 6.2 Conformance; 5.1.15 Assurance reporting | The assured basis narrated, or a statement on the page that the narrated basis is unassured | Conformance achievable without further assurance work |
| F-13 the FY2025 Safeguard exceedance is 44% acquitted on the face of the disclosure | Compliance with the scheme covering 81% of Scope 1 cannot be closed out | Carbon credit reporting with retirement and acquittal records | 5.1.12 Carbon Credit Reporting; 4.8.1 Abatement Principles | A facility-level acquittal statement naming the instruments | Conformance achievable: the retirement register already exists at serial-number level |
| F-14 the climate incentive vested on activity while emissions rose | Remuneration signals what the board rewards, and it rewarded studies | Metrics and targets linked to governance and reward | 4.9.2 Metrics & Targets; 4.9.4 Public Reporting | An emissions outcome measure in the incentive and in the annual scorecard | Non-conformance on outcome linkage |
| F-15 the 100% Transition Materials framing | A market position presented under a climate metric heading reads as decarbonisation | Use of claims and statements, with the classified quantity presented against its emissions | 4.9.1 Use of Claims and Statements; 4.9.4 Public Reporting; 1.1.3 Scope of Claims | The tier split and the emissions of the classified commodities presented together | Non-conformance on claim presentation |
| F-16 biogenic carbon dioxide moved inside Scope 1 without restatement | The Scope 1 series is not like-for-like across the change | Inventory presentation with biogenic emissions separately identified | 4.5 GHG Inventories; 4.5.5 Methodology; 5.1.10 Emissions Tracking | The biogenic figure stated separately as well as within the total, in every period | Conformance achievable: the figure is already published |
| F-17 unresolved cross-references in a statutory document | Two references in a document carrying a Directors' declaration lead nowhere | Public reporting quality controls | 4.9.4 Public Reporting; 5.1 Public Reporting requirements | A pre-issue check that no placeholder survives | Conformance achievable immediately |
South32's FY2026 climate disclosure does almost everything a reader could ask of the measurement and presentation layers, and then describes a commitment that is about to stop meaning what it says. The first mandatory year is delivered without qualification: a Directors' declaration, reasonable assurance over Scope 1 and both Scope 2 bases, an organisational boundaries table that says which basis governs which disclosure, quantified compliance and energy costs tied to financial-statement line items, an internal carbon price, and a five-year Scope 3 category series on two portfolio definitions in a year when none was required at all. The position against the target baseline is the first sentence of the emissions section rather than something to be reconstructed from a spreadsheet. The gross target has been set equal to the net target, which is a commitment to deliver the reduction physically rather than to buy it.
What sits on top of that is a target measured from 17.5 MtCO₂e whose baseline the announced sale of the aluminium value chain would reduce to about 1.7 MtCO₂e. The company publishes that figure, which is the disclosure that makes the position visible, and then stops: there is no pro-forma current position for the retained business, so a reader cannot tell whether it starts above or below its own new line. Meanwhile the year itself produced no net abatement. Emissions rose 4.7% on the basis the target and the audit both use, the 1.0% fall on the narrated basis is a divestment and a smelter closure offset by an electricity emission factor, value-chain emissions rose 22% under no reduction target, the renewable share of energy halved, and spending on decarbonising fell 68% to US$3.4 million against US$1,441 million of capital expenditure.
Three things would resolve most of what remains. Publish the residual portfolio's FY2026 emissions beside the 1.7 MtCO₂e pro-forma baseline and say whether the FY35 target is retained, recalibrated or withdrawn. State progress on one basis, the continuing-operations basis the baseline, the target definition and the audit opinion already share, and narrate the figures the auditor signed. And set an interim milestone, because a nine-year endpoint with no intermediate point, in a business whose composition is changing this fast, is not something a reader can hold anyone to.
This diagnosis is general information, published to support transparency, accountability and public debate on corporate climate disclosure. It sets out CRI's assessment of the publicly available climate disclosures of the organisation named above, for the reporting period stated, based on third-party information available at the review date. The assessment is made against CRI's Climate Disclosure Review Rules (version stated above), which use the CRI Net Zero Standard as the reference for a credible claim together with AASB S2 Climate-related Disclosures, and it gives reasons for each finding.
It assesses the disclosure, not the organisation's underlying climate performance or intent, and it does not allege illegality, misconduct, greenwashing or dishonesty. It is not tailored advice, nor legal, financial or investment advice, and it is not an audit, an assurance engagement or a certification. CRI does not accept liability for any error or omission in this analysis, or for any loss arising from use of or reliance on it.
AI tools help locate, extract and organise material from the source documents against a fixed rule set. Every rating and conclusion is reviewed and confirmed by CRI analysts; the rules, not the model, determine the outcome.
Organisations may contact CRI at robc@noco2.com.au to identify an error, provide relevant public information or request review of updated disclosures. Where a correction affects a finding, the diagnosis is updated and the change is noted. Further information about the review method is at noco2.com.au.
© Carbon Reduction Institute Pty Ltd, ABN 26 122 969 233. This report is protected by copyright. It reproduces third-party material for the purpose of criticism and review; any reproduction of this report not permitted under the Copyright Act 1968 (Cth) requires CRI's consent.
These annexes are the detailed working layer behind the findings in the body: the evidence base, rule application and traceability. Much of it is review working, retained for transparency and of interest to both the internal review team and external readers who want to see how each finding was reached.
| Document | Status | Criticality | Notes |
|---|---|---|---|
| Annual Report 2026 (FY ended 30 June 2026), incl. Addressing Climate Change section (pp.77-108), Independent Auditors' Review and Audit Report on specified Sustainability Disclosures (pp.109-113), Independent Practitioner's Limited Assurance Report (pp.114-117), Remuneration Report and financial statements | Reviewed | Critical | Primary audited source (A-01B). Carries the AASB S2 climate statements, the Directors' declaration under ss.296C and 296D, the climate note at Financial Report note 2(c), and the LTI climate measure. |
| Climate-related Reporting Methodology 2026 | Reviewed | Critical | Stated by the company to form part of the statutory Sustainability Report by cross-reference; named in the audit opinion for the organisational boundary and the Scope 1 and 2 methodology. Carries the FY35 target definition table, the recalculation triggers and the per-category Scope 3 method. |
| Sustainability Databook 2026 (Reporting boundaries, Climate Change, Portfolio, GHG Emissions, Other GHG Emissions, Energy, Emissions Limiting Regulations tabs) | Reviewed | Critical | Source of the FY2022 to FY2026 series on both portfolio bases, the Scope 3 category tables on both bases, the credit-retirement register and the Safeguard Mechanism tables. |
| Climate Change Action Plan 2025 | Reviewed | Critical | Stated by the company to constitute the Group's transition plan for AASB S2 purposes. Non-binding advisory resolution passed with 90% support at the October 2025 annual general meeting. |
| Annual Report 2025, Climate-related Risk and Reporting Methodology 2025, Sustainability Databook 2025 | Reviewed | Material but not critical | Prior-period comparators for §3.4 and Annex K, and the source for the FY2025 biogenic and Scope 2 factor-source positions. |
| Sustainability Standards and Frameworks Index 2026 | Not reviewed, document not provided | Material but not critical | AASB S2 and TCFD indices read where reproduced in the Methodology; SASB and Climate Action 100+ mapping read only where reproduced in the Annual Report. Framework-alignment findings limited accordingly; no adverse inference drawn (A-01A). |
| Climate Change Action Plan 2022 | Not reviewed, document not provided | Useful but optional | The 2022 commitments are assessed from the 2025 plan's own restatement. |
| NGER register FY2024-25 (Clean Energy Regulator), South32 Limited row | Reviewed | Useful but optional | Statutory anchor for the Australian Scope 1, Scope 2 location-based and net energy reconciliation (A-01C). Data as at 27/02/2026. The FY2026 register entry is not yet published; the company states the submission period runs to 31 October 2026. |
| Market releases dated 16 March 2026 (Mozal Aluminium care and maintenance), 30 April 2026 (Hermosa project update) and 1 July 2026 (Alcoa transaction) | Not reviewed, documents not provided | Useful but optional | Each is referenced in the Annual Report and the relevant content is reproduced there. Findings rest on the Annual Report's account, not on the releases. |
| Evidence ID | Source (doc, page/table) | What it shows | Linked claim / finding | Rule IDs | Status |
|---|---|---|---|---|---|
| E-01 | Databook 2026, GHG Emissions tab, Table A "Total GHG emissions" | FY2026 total operations: Scope 1 6.15; Scope 2 market-based 14.359; Scope 2 location-based 14.5; total Scope 1 and 2 market-based 20.5; Scope 3 28.6 MtCO₂e. Footnote (2): location-based total 20.7 Mt | §3.1; F-6, F-11, F-12 | G-06, G-07, S2-26, S2-28 | Confirmed |
| E-02 | Databook 2026, Other GHG Emissions tab, Table B "Total GHG emissions" | FY2026 continuing operations: Scope 1 5.9; Scope 2 market-based 14.3; Scope 2 location-based 14.4; total market-based 20.2; total location-based 20.3; Scope 3 28.5 MtCO₂e. Series runs FY2022 to FY2026; FY2021 is absent | F-6, F-7, F-12; §3.3, §3.4 | G-06, G-07, YOY-02, SEC-SF-11 | Confirmed |
| E-03 | AR 2026, p.82, "FY26 operational emissions" | "FY26 operational emissions were 20.5 Mt CO2-e, 1.0% lower than FY25 and 17.1% above the FY21 baseline of 17.5 Mt CO2e." Scope 1 decrease attributed to the Cerro Matoso divestment and the Mozal care-and-maintenance decision; Scope 2 increase attributed to higher Eskom-supplied electricity at Mozal and a higher Eskom emission factor | F-6, F-7, F-11; §3.3 | T-BASE-01, A-19, G-BAU, OUT-TB-03 | Confirmed |
| E-04 | AR 2026, p.83, "Our FY35 operational emissions reduction target" | "The FY21 target baseline, adjusted to reflect divestments and acquisitions completed to date, is 17.5Mt CO2-e." And: "had the aluminium value chain assets not formed part of our portfolio during the FY21 baseline year, our FY21 operational emissions baseline would have been approximately 1.7 Mt CO₂-e" | F-4, F-5; F-18 | T-BASE-01, G-10, YOY-06 | Confirmed |
| E-05 | AR 2026, pp.79-80, "FY27 review of our CCAP 2025 in response to aluminium value chain assets sale" | Binding conditional agreement announced 1 July 2026 to sell the aluminium value chain assets, excluding Mozal Aluminium, to Alcoa for an implied enterprise value of up to US$5.6 billion. Completion expected in H2 FY27 subject to shareholder approval. "Completion of the Transaction would materially change our portfolio, emissions profile, energy use and exposure to certain climate-related risks and opportunities." The FY35 target, pathways, assumptions, initiatives, governance and performance measures are all to be reassessed in FY2027 | F-5; F-18 | T-BASE-01, T-05, S2-38, YOY-06, A-21 | Confirmed |
| E-06 | Methodology 2026, pp.5-6, FY35 target definition table | Type: Absolute. "Reduction: Net, 50%. Gross, 50% (no current planned use of carbon credits)". Boundary: Scopes 1 and 2, operational control. Measurement: Scope 2 by the market-based method. Baseline adjusted for divestment of Cerro Matoso (1 December 2025), Metalloys, Illawarra Metallurgical Coal, South Africa Energy Coal and TEMCO, giving 17.5 MtCO₂e | F-1; §3.1 | T-14, S2-41, T-BASE-01, S2-28 | Confirmed |
| E-07 | Methodology 2026, p.6, "Key adjustments made to baseline year" and "Recalculation of baseline year operational emissions" | "Mozal Aluminium was placed into care and maintenance in March 2026. This did not result in rebaselining of the target as it remains within our operational control and continues to be included within continuing operations." Recalculation triggers: structural change including "completion of the Transaction", methodology or factor change above a 5% variance, and significant error | §3.4; F-16 | G-10, T-BASE-01 | Confirmed |
| E-08 | Methodology 2026, p.6, "Process for monitoring progress towards the target" | "We have not set any interim targets. We have indicative milestones for the maturation of external dependencies to inform feasibility of our preferred pathway to secure an affordable, low-carbon electricity solution for Hillside Aluminium." | F-8 | T-05, T-13, S2-40, SEC-MIN-05 | Confirmed |
| E-09 | Methodology 2026, p.6, "Third-party validation" and "External assurance" | "We have not obtained third-party validation of our FY35 target." "We obtain reasonable assurance over our externally reported performance against the target." | §2.3; F-12 | T-SBTi-01, GOV-14 | Confirmed |
| E-10 | AR 2026, pp.110-112, Independent Auditors' Review and Audit Report on specified Sustainability Disclosures | Audit (reasonable assurance) over AASB S2 subparagraphs 29(a)(i)(1)-(2) and 29(a)(ii)-(v): Total Scope 1 (continuing operations) 5.9; Total Scope 2 market-based (continuing) 14.3; Total Scope 2 location-based (continuing) 14.4 MtCO₂e, plus the Methodology's organisational boundary and Scope 1 and 2 methodology. Unmodified opinion under ss.296A(2), 296C and 296D. Review (limited assurance) over governance (para 6) and strategy risks and opportunities (subparas 9(a), 10(a), 10(b)), unmodified. Other Matter: the FY2025 and FY2024 comparatives "were not subject to our audit engagement" | F-12; §2.3 | GOV-10 to GOV-16, A-11, S2-01 to S2-06 | Confirmed |
| E-11 | AR 2026, pp.114-115, Independent Practitioner's Limited Assurance Report | Voluntary limited assurance over Select Sustainability Information: Total Scope 3 GHG emissions 28.6 MtCO₂e and Total energy (managed basis) 138 PJ, plus safety, biodiversity and water quantities and three ICMM qualitative subject matters. Emissions intensity is not in the assured set | F-12; F-23 | A-11, GOV-14, S3A-16 | Confirmed |
| E-12 | AR 2026, p.77-78, "Our climate-related disclosures" and "AASB S2 Directors' declaration" | The Sustainability Report is defined as the Addressing Climate Change section plus cross-referenced sections plus the Methodology 2026. "Our CCAP 2025 constitutes the Group's transition plan for the purposes of AASB S2." Transitional relief applied for comparatives; "Scope 3 emissions are disclosed voluntarily and, consistent with the transitional relief available to South32 for FY26, have not been prepared in accordance with AASB S2." The December 2025 Amendments to AASB S2 are early adopted. Directors' declaration under ss.296C and 296D, signed 27 August 2026 | §2.3; C-09 | S2-01 to S2-06, L-01 to L-14 | Confirmed |
| E-13 | AR 2026, pp.107-108, "Organisational boundaries" table | Maps each disclosure to its boundary and presentation basis. Energy and Scope 1 and 2 on operational control; equity share supplementary and outside the AASB S2 disclosures and outside assurance; Scope 3 category-specific with downstream on an equity-share basis. "Where continuing operations information is disclosed, the same basis is applied to comparative periods, baseline years and historical performance measures presented alongside the disclosure to support comparability over time." "Continuing operations energy consumption and Scope 1 and Scope 2 emissions … are subject to reasonable assurance." | F-6, F-12; §3.1 | G-04, G-05, G-20, S2-25 | Confirmed |
| E-14 | Databook 2026, GHG Emissions tab, by source, by gas, by commodity and asset, by operation | FY2026 total operations Scope 1 and 2 by source: electricity 14.4, coal and coke 3.6, natural gas 1.8, distillate and gas 0.4, fugitive 0.2, other 0.1. By operation: Hillside 12.4, Mozal 3.9, Worsley 3.2, Australia Manganese 0.2, South Africa Manganese 0.2, Cannington 0.1, greenfields 0.1, divested 0.4 | §3.1, §3.3; F-5 | G-06, SEC-MIN-09 | Confirmed |
| E-15 | Databook 2026, GHG Emissions and Other GHG Emissions tabs, Scope 3 by category and emission type | Fifteen categories stated for FY2022 to FY2026 on both bases. FY2026 total operations: C1 2.8, C3 1.5, C4 0.9, C9 0.1, C10 21.8, C15 1.4; C5, C8 and C12 not calculated; C11, C13 and C14 not applicable. C10 split alumina 9.6, aluminium 1.1, copper 0.3, manganese 10.8 | F-2, F-9; §3.1 | S3-01 to S3-31, S2-29, G-15 to G-19 | Confirmed |
| E-16 | Databook 2026, GHG Emissions tab, Table A footnote (4); AR 2026, p.86 footnote 34 | "FY25 scope 3 data has been restated following the identification of a third-party calculation error. FY25 values have been revised as follows: Total: 23.5 (previously 22.7); Category 1 Purchased goods and services: 3.6 (previously 3.0); Category 1 Other purchased goods and services: 1.8 (previously 1.2); Category 4 Upstream transportation and distribution: 0.8 (previously 0.6)." | §3.4 | G-10, GHG-STD-08, YOY-03 | Confirmed |
| E-17 | Databook 2026, GHG Emissions tab, Table A footnote (1); Methodology 2026 p.8; Databook 2025 Table A footnote (3) | FY2026: "In accordance with AASB, for FY26 0.09 Mt CO2 biogenic emissions are being included in our Scope 1 emissions totals." Methodology: "While the GHG Protocol Corporate Standard requires biogenic CO2 emissions to be separately identified for disclosure purposes, under AASB S2 biogenic emissions are included within the relevant Scope 1, Scope 2 and Scope 3 emissions disclosures". FY2025 databook stated of the 0.05 Mt figure: "These emissions do not form part of our Scope 1 inventory." | F-16 | GHG-STD-05, G-10, GHG-STD-08 | Confirmed |
| E-18 | Databook 2026, Energy tab | Total operations energy 137.9 PJ (FY2025 159); renewable sources 12.5 PJ, 9.1% (FY2025 25 PJ, 16%). Continuing basis 131.3 PJ and 10.8 PJ, 8.2% (FY2025 142.3 and 21.4, 14.8%). Mozal Aluminium energy 26.9 PJ against 39.0 in FY2025. Renewable sources defined as Worsley biomass, Cahora Bassa hydroelectricity to Mozal and Colombian hydroelectricity to Cerro Matoso to divestment | §3.3, §3.4 | E-01 to E-24, S2-28 | Confirmed |
| E-19 | AR 2026, p.86, "FY26 Scope 3 emissions" | Scope 3 28.6 MtCO₂e, "22% higher than FY25". Category 10 up 50% "due to higher alumina sales volumes and increased manganese ore sales following the restart of operations at Australia Manganese"; Category 4 up on higher shipment volumes; Category 1 down 22% on the Cerro Matoso divestment and the Mozal transition; Category 9 down 20%; Category 11 no longer applicable | F-9; §3.3, §3.4 | S3-16, A-19, G-BAU, YOY-02 | Confirmed |
| E-20 | AR 2026, p.87 and footnote 35 | "In FY26, we engaged with over 80% of key suppliers"; "In FY26, we engaged with over 90% of key customers". Footnote 35: "Engagement percentage for our measurable objectives is tracked based on the number of key suppliers (upstream) and quantity of product sold (downstream). We define 'key suppliers' as those with ongoing relationships that contribute to our upstream transition risk exposure, and 'key customers' as those with ongoing, high-value relationships." | F-9; F-27 | T-SUP-03, T-PROC-05, T-COV-02 | Confirmed |
| E-21 | AR 2026, p.87, "Resourcing climate-related activities"; repeated p.97 | "FY26 decarbonisation expenditure totalled US$3.4 million, including energy efficiency technology at Hillside Aluminium and studies at Worsley Alumina." | F-10 | T-06, S2-35, SEC-MIN-04 | Confirmed |
| E-22 | AR 2026, p.29, Capital expenditure (South32 share) | FY2026 total capital expenditure including equity-accounted investments US$1,441M (FY2025 US$1,353M): safe and reliable 207, improvement and life extension 111, growth 711, intangibles and capitalised exploration 57, discontinued 8, equity-accounted 347 | F-10 | T-06, SEC-MIN-04 | Confirmed |
| E-23 | AR 2026, p.81, "Allocating capital towards Transition Materials" | US$711M growth expenditure at Hermosa, US$241M at Sierra Gorda and US$34M of greenfield exploration are presented as capital allocated to Transition Materials. AR 2026 p.104 lists "Transition material capital expenditure" and "Decarbonisation expenditure" as two entries under the same cross-industry metric heading | F-10, F-15 | SEC-MIN-06, SEC-MIN-08, S2-29 | Confirmed |
| E-24 | AR 2026, p.104, Transition materials metrics | Commodities classified as Key Transition Materials (copper) and Other Transition Materials (zinc-lead-silver, manganese, alumina, aluminium) under the Climate Action 100+ Net Zero Standard for Diversified Mining. "These Transition Materials represent 100% of our portfolio on a copper equivalent basis." Sierra Gorda copper is 87 kt of copper-equivalent production, 10%. Footnote 25 excludes gold; footnote 66 states percentages exclude Cerro Matoso | F-15; C-07 | SEC-MIN-06, SEC-MIN-08, OUT-TB-02, T-COV-02 | Confirmed |
| E-25 | AR 2026, p.84, "FY26 progress update" | Hillside: AP3XLE energy efficiency technology in 66% of pots at FY2026 end, electricity efficiency 13.51 MWh per tonne of aluminium; Eskom joint working group established; nuclear-derived environmental attribute certificates not pursued further. Worsley: alternative steam supply study progressed; biomass consumption "nearly doubled … contributing to a 3% reduction in Scope 1 emissions year-on-year"; steam electrification pre-feasibility phase one complete, identifying a technically feasible pathway with "high capital intensity and current electricity market conditions" as significant barriers; two boilers converted in FY2024 "reducing the operation's annual emissions by approximately 10% relative to the FY21 baseline" | §3.3; F-21, F-22; P3 | A-19, G-BAU, SEC-MIN-12, T-06 | Confirmed |
| E-26 | AR 2026, p.83, "Potential pathways" and "Carbon credits for offsetting emissions" | Preferred pathway: transition Hillside's electricity supply to low-carbon sources, requiring "multiple gigawatts of renewable electricity supply, substantial grid infrastructure upgrades, and enabling regulatory and market conditions … beyond 2031". Alternative pathway: close the smelter on expiry of the electricity agreement in 2031, which "formed the basis for certain long-term financial reporting assumptions". "we have not, to date, acquired carbon credits for the purpose of offsetting emissions in our net emissions reporting or supporting achievement of our FY35 target" | F-1; F-21 | T-DEP-04, G-11, E-08, SEC-MIN-01 | Confirmed |
| E-27 | AR 2026, p.82, "Mozal Aluminium: Care and Maintenance"; Databook 2026 Reporting boundaries tab | "In March 2026, Mozal Aluminium was placed into care and maintenance after the operation was unsuccessful in securing a sufficient and affordable long-term electricity supply". Placed on care and maintenance 15 March 2026. "While energy use and associated emissions have reduced significantly, residual emissions continue to be reported because the smelter remains under our operational control." Mozal FY2026 total emissions 3.9 MtCO₂e against 3.6 in FY2025 | §3.3, §3.4; F-18 | G-04, G-20, T-BASE-01, SEC-MIN-07 | Confirmed |
| E-28 | Databook 2026, Reporting boundaries tab | Operated portfolio, ownership percentages and joint venture partners; development projects; non-operated joint ventures (Sierra Gorda 45%, Alumar refinery 36%, Alumar smelter 40%, MRN 33%, Ambler Metals 50%); divested operations with dates, Cerro Matoso 1 December 2025. States the Alcoa transaction was announced after 30 June 2026 and does not affect FY2026 boundaries | §3.1, §3.2; E-45 | G-04, G-05, SEC-INV-LT-17 | Confirmed |
| E-29 | Databook 2026, Emissions Limiting Regulations tab | FY2025 Safeguard Mechanism baselines and covered Scope 1 emissions: Cannington 106,486 / 122,968; Groote Eylandt (GEM01) 100,000 / 135,299; Worsley Alumina 3,087,057 / 3,218,588 tCO₂e. FY2024 and FY2023 series also given. FY2026 baselines to be published by the Clean Energy Regulator after the submission period closing 31 October 2026 | F-13; F-20, F-25 | DR-05, A-01C, SEC-MIN-11 | Confirmed |
| E-30 | Databook 2026, Emissions Limiting Regulations tab, "FY26 Carbon credits retired" | Seven Australian Carbon Credit Unit retirements totalling 79,981 units, each with project, vintage, method, serial number range, cancellation date, registry and facility, all "Surrender of ACCUs to meet regulatory liability under the Australian Safeguard Mechanism … Excess emissions from 2024-2025 National Greenhouse and Energy Reporting". Five South African retirements totalling 100,846 units against CY2024 and CY2025 carbon tax liabilities | F-3, F-13; F-20 | E-08 to E-22, G-11 | Confirmed |
| E-31 | Databook 2026, Emissions Limiting Regulations tab, South Africa voluntary carbon budget | CY2021 to CY2025 budget period: Hillside Aluminium carbon budget 6,852,277 against Scope 1 of 6,706,552 tCO₂e; South Africa Manganese 569,460 against 531,405. Both within budget | §2.3 | DR-05, SEC-MIN-11 | Confirmed |
| E-32 | AR 2026, p.97, TR1 "Decarbonisation constraints", Financial effects | FY2026 total energy costs US$1,091 million, 49% of the Group's US$2.2 billion expenditure on market-traded consumables and energy, of which US$960 million (88%) is alumina and aluminium. Referenced to Financial Report note 5 | §5.2; F-10 | S2-33 to S2-37 | Confirmed |
| E-33 | AR 2026, p.99, TR2 "Emissions-limiting regulations", Financial effects | FY2026 compliance costs US$6.3 million: Safeguard Mechanism 3.7, South Africa carbon tax 1.1, other 1.5, covering 81% of Scope 1. No EU CBAM costs disclosed because the mechanism took effect on 1 January 2026 and estimates "cannot be reliably estimated". Anticipated future effects not quantified on a stated measurement-uncertainty ground | §2.3, §5.2; F-29 | S2-33 to S2-37, DR-05 | Confirmed |
| E-34 | AR 2026, p.100 and Financial Report note 2(c) | "From FY40, our base case assumes a single global carbon price of US$71 per tonne CO2-e (real July 2026)", applied to all Scope 1 and 2 emissions, based on enacted schemes less allowable abatements until FY39. Not applied in internal transfer pricing | §2.3 | S2-36, GOV-08 | Confirmed |
| E-35 | AR 2026, Financial Report note 2(c), "Portfolio resilience" | "Overall, the Group's portfolio is resilient under both scenarios, notwithstanding specific asset-level exposures at Hillside Aluminium." "The Hillside Aluminium LoOP is currently limited to 2031 … Extension of the Hillside Aluminium LoOP beyond 2031 is highly dependent on securing an affordable source of low-carbon energy." Group valuations include the cost and benefit of identified initiatives necessary to meet the FY35 target; the 2050 pathway is not fully defined so its costs are not included | §5.2; F-28; C-11 | S2-33 to S2-37, T-06 | Confirmed |
| E-36 | AR 2026, p.91, scenario assumptions | Accelerated Transition (1.5°C) and Fragmented Transition (2.8°C), both developed in FY2025 and retained for the FY2026 resilience assessment. "Global explicit carbon price US$208/t CO2 by 2040 increasing to US$263/t CO2 by 2050" under the first, "US$71/t CO2 from FY40 onwards" under the second. Base case assumes at least 2°C and up to around 2.8°C by 2100 | §5.2; C-11 | S2-30 to S2-35 | Confirmed |
| E-37 | AR 2026, pp.101 and footnote 37, physical risk | Asset-level assessment under SSP2-4.5 and SSP5-8.5, downscaled CMIP6 ensembles sourced from Jupiter Intelligence, presented for SSP5-8.5 to 2050 relative to 2020. Carried into life-of-operation plans, valuations and closure and rehabilitation provisions. Climate Adaptation and Resilience Plan with five initiatives | §5.2; P3 | N-01 to N-03, S2-33 | Confirmed |
| E-38 | AR 2026, p.164, FY23 LTI strategic measures assessment | Climate change measure: weighting 10%, outcome 6.5%. Assessed on the Worsley coal alternative steam supply study reaching prefeasibility-define, the waste heat to digestion study concluding capital intensity and expected reduction "were insufficient to justify investment", conversion of an additional 10% of Hillside pots to AP3XLE for 66% total, battery electric trials at Cannington, the Eskom joint working group and the Electric Mine Consortium workstream. Total strategic measures 15.5% of 20%; the 80% TSR portion lapsed in full | F-14 | GOV-01 to GOV-06, A-11 | Confirmed |
| E-39 | AR 2026, pp.162-163, FY26 Business Scorecard; p.59 | Scorecard categories: safety and health, workforce and diversity, environment (nature-related milestones across water, biodiversity and pollution), social, production, cost, EBITDA and Hermosa milestones. No greenhouse gas or emissions measure. "In FY26, 35% of the performance metrics in our Business Scorecard … were sustainability-related." Scorecard outcome 108.0% of target | F-14 | GOV-01 to GOV-06 | Confirmed |
| E-40 | Methodology 2026, pp.9-10, "Value chain emissions" | Categories included: 1, 3, 4, 6, 7, 9, 10, 15. Excluded with stated reasons: 2 (inside Category 1), 5 (not material, waste utility spend inside Category 1), 8 (inside Scope 1 under operational control), 11 (no applicable products), 12 (not material, metals and minerals with minimal end-of-life emissions), 13 and 14 (none). "Boundary overlap … some double counting may be inherent due to our position in the value chain and may inflate our reported total Scope 3 emissions." | §3.1; F-26 | S3-25, S3-26, G-15 to G-19, G-20 | Confirmed |
| E-41 | Methodology 2026, p.14, Category 10 | Exclusions: "we also produce zinc and lead concentrates, molybdenum, gold, silver and nickel … the production volumes for these commodities (and their associated emissions) are not significant compared to those for alumina, aluminium, copper and manganese. As a result, emissions from the downstream processing of these products have been excluded at this stage." Calculation basis equity share; 2024 CRU aluminium smelting emission factors; South32 smelters excluded from the industry-average calculations | F-24 | S3-25, S3-EST, A-21 | Confirmed |
| E-42 | Methodology 2026, pp.7-8, Scope 2; Methodology 2025, p.8 | FY2026 location-based factor sources: NGER Determination 2008 as amended (2025) for Australia; "South Africa's 2023 Grid Emissions Factor Report (2025)" for South Africa Manganese and Hillside; EDM factor for Mozal; eGRID for Hermosa; UPME for Cerro Matoso. FY2025 used "South Africa's 2022 Grid Emissions Factor Report (2024)". Market-based sources: NGER for Australia, the Eskom electricity factor for South Africa, the EDM factor for Mozambique | F-11; F-19 | S2-28, E-01 to E-07, G-10 | Confirmed |
| E-43 | Methodology 2026, p.3, footnotes 2 and 3 | "Details of operations not wholly owned by South32 Limited or its subsidiaries and for which South32 manages the operation, are on page [xx] of the 2026 Annual Report." The same placeholder appears in footnote 3 | F-17 | OUT-09, A-11 | Confirmed |
| E-44 | NGER register FY2024-25, SOUTH32 LIMITED (ABN 84 093 732 597), data as at 27/02/2026 | Scope 1 3,476,916 tCO₂e; Scope 2 location-based 28,306 tCO₂e; net energy 52,156,288 GJ. The three Australian facilities' FY2025 Safeguard covered Scope 1 emissions sum to 3,476,855 tCO₂e | §5.3; F-25 | A-01C, DR-02, DR-05 | Confirmed |
| E-45 | Databook 2026, Other GHG Emissions tab, Table B disaggregation | AASB S2 paragraph 29(a)(iv) split for FY2026 continuing operations: consolidated group Scope 1 1.7, Scope 2 market-based 11.0, location-based 9.3; investments in joint ventures under operational control Scope 1 4.2, Scope 2 market-based 3.2, location-based 5.2 | §2.3; §3.1 | S2-27, S2-29 | Confirmed |
| E-46 | AR 2026, p.78 and p.80 | "A non-binding advisory resolution on the 2025 CCAP received strong shareholder support at our Annual General Meeting in October 2025, with 90% of votes cast in favour." | Context for OUT-STK-05 | OUT-TB-02, GOV-01 | Confirmed |
| E-47 | AR 2026, p.86, Scope 3 by position in the value chain | Upstream 5.1 MtCO₂e (18%), downstream 23.4 MtCO₂e (82%), continuing operations. Category 15 split: Brazil Alumina 59%, Brazil Aluminium 27%, Sierra Gorda 14% | §3.1, §3.2 | S3-25, SEC-INV-LT-17 | Confirmed |
| E-48 | Methodology 2026, p.4, Metric 1 and Metric 2 | Copper-equivalent production is presented on an equity share basis for Metric 1. For Metric 2, emissions intensity, "emissions and CuEq production are calculated on the same operational control, 100 per cent basis". Both use FY2025 realised prices for all periods. "A reduction in emissions intensity does not necessarily indicate a reduction in absolute Scope 1 and Scope 2 emissions." | F-23 | T-14, S2-29, T-COV-02 | Confirmed |
| E-49 | AR 2026, p.106, emissions-limiting regulation metrics | Scope 1 covered under an emissions-limiting regulation: FY2026 5.0 MtCO₂e and 81%; FY2025 5.5 and 74%; FY2024 7.2 and 76% | F-13; §2.3 | DR-05, S2-29 | Confirmed |
| Claim ID | Wording / paraphrase | Claim object | Claim source & basis (OUT-TB-15) | Doc & location | Strength | Audience | Evidence req/found/missing | Triggered scans | Rule IDs | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| C-01 | "Halve our net operational emissions by FY35 from FY21 levels" | Scope 1 and Scope 2 on an operational-control boundary, market-based Scope 2, continuing-operations portfolio, adjusted baseline 17.5 MtCO₂e | Self-declared. Not third-party validated, and the company states so | AR 2026 p.80, p.83; Methodology 2026 pp.5-6; Financial Report note 2(c) | Strong (a target, with an identified pathway on the company's own definitions) | All | Required: baseline, current position on the target basis, pathway quantum, credit treatment, post-transaction treatment. Found: baseline, current position, gross equals net, recalculation triggers. Missing: pathway quantum, interim milestone, residual-portfolio position | Target boundary, baseline, progress calculation, gross vs net, offsets, method changes, remuneration link | T-01 to T-14, T-BASE-01, T-DEP-04, S2-38 to S2-42 | Concern: F-5 to F-8 |
| C-02 | "FY26 operational emissions were 20.5 Mt CO2-e, 1.0% lower than FY25 and 17.1% above the FY21 baseline of 17.5 Mt CO2e" | Scope 1 plus market-based Scope 2, total operations, against a continuing-operations adjusted baseline | Self-declared; the components are published but the 20.5 figure is outside the audit scope | AR 2026 p.82 | Strong (a stated figure and a stated position) | All | Required: matching bases. Found: both series published and labelled at p.105. Missing: a like-for-like comparison | Baseline comparability; real vs accounting | T-BASE-01, A-19, G-BAU, OUT-TB-03 | Concern: F-6. Arithmetically correct and unfavourable to the company |
| C-03 | "Scope 2 emissions increased 8% (1.1 Mt CO2-e) from FY25, reflecting higher consumption of Eskom-supplied electricity by Mozal Aluminium and an increase in Eskom's emissions factor" | Market-based Scope 2, total operations | Self-declared; basis not named in the sentence | AR 2026 p.82 | Strong | All | Required: the basis label and the location-based movement. Found: both bases tabulated at p.105. Missing: any explanation of the 16.2% location-based fall | Location vs market-based, dual reporting, real vs accounting | S2-28, G-07, OUT-TB-03, A-19 | Concern: F-11; cannot verify: F-19 |
| C-04 | "FY26 Scope 3 emissions totalled 28.6 Mt CO2-e, 22% higher than FY25" | Total Scope 3, total operations | Assured at limited level | AR 2026 p.86; Databook 2026 | Strong (a stated figure and movement) | All | Required: the comparative and its restatement. Found: the restated FY2025 figure of 23.5 with the affected categories quantified. Missing: nothing on this claim | Scope 3 categories, restatement, comparability | G-10, GHG-STD-08, S3-16, YOY-03 | No apparent issue on the claim; the concern is coverage (F-9) |
| C-05 | "we engaged with over 80% of key suppliers" and "we engaged with over 90% of key customers" against measurable objectives of 80% each by FY2028 | Counts of key suppliers, and quantity of product sold for customers | Self-declared, on a denominator the company defines but does not publish | AR 2026 p.87 and footnote 35 | Moderate (a quantified objective on an undisclosed denominator) | Institutional and retail investors, public | Required: the denominators. Found: a definition of the measure for each side. Missing: any count or volume | Coverage claim denominator; engagement vs reduction | T-COV-02, T-SUP-03, T-PROC-05 | Concern: F-9; cannot verify: F-27 |
| C-06 | "Our FY35 target covers 100% of our operational emissions" | Target coverage of Scope 1 and Scope 2 | Self-declared | AR 2026 p.83 | Strong | All | Required: confirmation that no operational source is outside the target. Found: the target boundary is Scopes 1 and 2 on operational control, matching the inventory boundary | Coverage claim; target boundary vs inventory boundary | T-COV-02, T-01, OUT-TB-21 | No apparent issue on coverage; the concerns are progress and the pending recalibration |
| C-07 | "Under the Climate Action 100+ Net Zero Standard for Diversified Mining, all commodities in our portfolio are classified as Transition Materials … These Transition Materials represent 100% of our portfolio on a copper equivalent basis" | Copper-equivalent production classified under a third-party framework | Third-party classification framework, applied by the company to its own portfolio | AR 2026 p.81 and p.104, footnotes 25 and 66 | Strong (an unqualified 100%) | Retail investors, public, institutional investors | Required: the classification tiers and the denominator. Found: both, with copper the only key-tier commodity at about 10% of copper-equivalent production, and gold and Cerro Matoso excluded from the denominator. Missing: the emissions of the classified commodities presented alongside | Transition-materials narrative vs emissions performance; coverage denominator | SEC-MIN-06, SEC-MIN-08, OUT-TB-02, T-COV-02 | Concern: F-15 |
| C-08 | "No carbon credits retired in FY26 were included in the calculation of our net Scope 1 and Scope 2 emissions" and "Gross, 50% (no current planned use of carbon credits)" | The net Scope 1 and 2 figure, and the character of the FY35 target | Self-declared, with a serial-number-level retirement register published beside it | Databook 2026 GHG tab footnote (3) and Emissions Limiting Regulations tab; Methodology 2026 p.5 | Strong | All | Required: the retirement register and the gross target statement. Found: both | Offset retirement evidence; gross vs net | E-08 to E-22, G-11, T-14, S2-41 | No apparent issue; basis of positives F-1 and F-3 |
| C-09 | "South32 has prepared climate-related disclosures … in accordance with the requirements of AASB S2 Climate-related Disclosures and the Corporations Act 2001" | The Sustainability Report as defined | Statutory, with a Directors' declaration and an unmodified audit opinion and review conclusion | AR 2026 pp.77-78, pp.110-112 | Strong, and appropriately bounded by the disclosed reliefs | Regulators, all | Required: the opinion, the declaration and the reliefs. Found: all three, with the Scope 3 relief and the comparatives relief expressly stated | Applicability gate; AASB S2 compliance | S2-01 to S2-06, L-01 to L-14 | No apparent issue |
| C-10 | "had the aluminium value chain assets not formed part of our portfolio during the FY21 baseline year, our FY21 operational emissions baseline would have been approximately 1.7 Mt CO₂-e" | The FY2021 target baseline on a pro-forma post-transaction portfolio | Self-declared pro-forma, published voluntarily ahead of the recalculation | AR 2026 p.83 | Strong, and unusually specific for a pro-forma | Institutional and retail investors, public | Required: the corresponding pro-forma current position. Found: the baseline only. Missing: the FY2026 position on the same basis | Baseline recalculation; structural change | T-BASE-01, G-10, YOY-06 | Basis of positive F-4 and of finding F-5 |
| C-11 | "Overall, the Group's portfolio is resilient under both scenarios, notwithstanding specific asset-level exposures at Hillside Aluminium" | Portfolio resilience under the Accelerated Transition and Fragmented Transition scenarios | Self-declared, inside the audited financial statements | AR 2026 Financial Report note 2(c); AR 2026 p.94 | Moderate, and expressly qualified | Institutional investors, regulators | Required: the scenario assumptions and the exception. Found: both scenarios with carbon prices, and the Hillside life-of-operation limit of 2031 with the closure pathway stated | Scenario analysis; transition risk; financial effects | S2-30 to S2-37, N-04 | No apparent issue; the limitation is stated against the company's own position |
| C-12 | "In accordance with AASB, for FY26 0.09 Mt CO2 biogenic emissions are being included in our Scope 1 emissions totals" | Scope 1 measurement basis | Self-declared method position, stated against the acknowledged GHG Protocol requirement | Databook 2026 Table A footnote (1); Methodology 2026 p.8 | Moderate | Carbon accountants, regulators | Required: the amount and the treatment of prior years. Found: the amount. Missing: restated comparatives or a separate line in every year | Method change; comparability | GHG-STD-05, G-10, GHG-STD-08 | Concern: F-16 |
| C-13 | "we report two GHG emissions data sets: Total operations basis … and Continuing operations basis" with the boundaries table stating that continuing-operations information is presented against continuing-operations baseline years | The two published portfolio series and the basis convention | Self-declared, published in the data book and in the Annual Report boundaries table | Databook 2026 GHG tabs; AR 2026 pp.107-108 | Moderate | Carbon accountants, institutional investors | Required: both series and the stated convention. Found: both, complete for five years, and the convention. Missing: adherence to the convention in the progress statement | Comparability; multi-period series | YOY-02, G-10, GHG-STD-08 | Accurate, and the basis of positive F-2; the concern is that the progress statement departs from it (F-6) |
| C-14 | "We have a long-term goal to achieve net zero operational emissions by 2050" | Scope 1 and Scope 2, with a separate all-scopes net zero goal referenced for Scope 3 | Self-declared, and expressly labelled a "goal", which the company defines as an aspiration for which no pathway has been identified | AR 2026 p.80, p.85; Financial Report note 2(c) footnote 6 | Moderate: the company's own definition removes the implication of a pathway | Retail investors, public | Required: pathway, residual treatment. Found: neither, and the company says so, adding that it plans to review the pathway in light of the sale. Missing: both, disclosed as such | Net zero claim, residual emissions, offsets, transition plan | T-05, T-13, E-08, S2-40, A-21 | Cannot verify by construction; not a claim defect |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D1-01 | FY2026 is South32's first mandatory AASB S2 period. Climate statements are prepared under ss.296A, 296C and 296D with a Directors' declaration dated 27 August 2026, an unmodified audit opinion over Scope 1 and both Scope 2 bases and an unmodified review conclusion over governance and strategy (E-10, E-12). Transitional reliefs for comparatives and for Scope 3 are applied and disclosed; the December 2025 amendments are early adopted (L-01 to L-14, S2-01 to S2-06) | No apparent issue: the standard is met on its face with unmodified opinions | The mandatory architecture is delivered in full: the paragraph 29(a)(iv) consolidated-versus-joint-venture split on both Scope 2 bases (E-45), an organisational boundaries table (E-13), quantified current financial effects referenced to financial-statement line items (E-32, E-33), an internal carbon price (E-34) and cross-industry metrics with page references. Obtaining reasonable assurance over Scope 1 and 2 is the statutory minimum for a first-year filer, so it is baseline and is not credited (A-16) | No apparent issue · High | A reader can rely on the Scope 1 and 2 figures as audited statutory disclosures | Not applicable |
| D1-02 | The Scope 3 relief is exercised: "Scope 3 emissions are disclosed voluntarily and, consistent with the transitional relief available to South32 for FY26, have not been prepared in accordance with AASB S2" (E-12). Comparatives are also relieved except where voluntarily presented | No apparent issue: both reliefs are available and both are disclosed | Decision-usefulness limitation, small. Scope 3 is 58% of the combined footprint and sits outside the standard's preparation requirements for the year, though it carries voluntary limited assurance and a five-year category series on two bases (E-11, E-15). A-21 applies to the stated intention to prepare Scope 3 under the standard in due course: neither a fault nor a credit | Minor limitation · High | A reader relying on the Scope 3 figures is relying on a voluntary disclosure, which the company states | Prepare Scope 3 under the standard at the first period the relief lapses |
| D1-03 | The Climate-related Reporting Methodology 2026 is stated to form part of the statutory Sustainability Report and is named in the audit opinion, and carries two unresolved "[xx]" page cross-references (E-43) | Potential compliance concern, low severity: a statutory document carrying a Directors' declaration contains unresolved placeholders | Decision-usefulness concern, minor. The two references point to where non-wholly-owned operations are listed, which is material to the boundary discussion the placeholders sit inside | Minor limitation · High | A reader following the cross-reference reaches nothing | Resolve the references; add a placeholder check to the pre-issue process (F-17) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D2-01 | Scope 1 is decomposed by source, by gas, by operation and by commodity and asset across five years (E-01, E-14). FY2026 total operations 6.2 MtCO₂e: coal and coke 3.6, natural gas 1.8, distillate and gas 0.4, fugitive 0.2, other 0.1. Six greenhouse gases enumerated; nitrogen trifluoride excluded with a stated reason. No combined Scope 1 plus 2 figure is offered without its components (G-06, SEC-MIN-09) | No apparent issue | No apparent issue, baseline (not credited). Source-level disclosure is what SEC-MIN-09 requires of an energy-intensive producer | No apparent issue · High | A reader can see which Scope 1 sources move and why | Not applicable |
| D2-02 | One reporting year produces five legitimate Scope 1 and 2 totals: 20.5 market-based and 20.7 location-based on total operations, 20.2 and 20.3 on continuing operations, and 19.9 on an equity-share basis (E-01, E-02, E-45). Each is labelled and each reconciles internally. The narrative uses the first and the audit covers the third and fourth (E-03, E-10) | No apparent issue: dual reporting and dual portfolio presentation are both permitted and both disclosed, and the boundaries table maps them (E-13) | Decision-usefulness concern. The reader must select a total, and the disclosure's own narrative and its own audit opinion select different ones. Workable: the reader's action is to take the operational-control, market-based continuing-operations total of 20.2 MtCO₂e as the audited footprint and the total-operations 20.5 as the narrated one; the disclosed data are the labelled p.105 tables and the boundaries table | Decision-usefulness concern · High | A reader quoting "the audited figure" from the narrative would be quoting an unaudited one | Narrate the audited figures and label the basis at every point of use (F-12) |
| D2-03 | Biogenic carbon dioxide of 0.09 MtCO₂e is included inside Scope 1 for FY2026, having been expressly outside the Scope 1 inventory in the prior period, with prior years not restated (E-17). The company acknowledges the GHG Protocol Corporate Standard requires separate identification and states AASB S2 as its basis. The amount is 1.5% of Scope 1, below the company's own 5% recalculation threshold (E-07) | Minor limitation: a stated departure from the Corporate Standard, reasoned and sized | Decision-usefulness concern, minor. The Scope 1 series is not like-for-like across the change, and the change runs against the year's principal abatement, since increased biomass combustion at Worsley both lowers fossil Scope 1 and raises the biogenic figure now counted inside it (E-25) | Minor limitation · High | A reader comparing FY2026 Scope 1 with earlier years is comparing across a definitional change | State the biogenic figure separately as well as within the total, in every period (F-16) |
| D2-04 | The FY2025 Scope 3 total is restated from 22.7 to 23.5 MtCO₂e following a third-party calculation error, with Categories 1 and 4 quantified and the sub-line for other purchased goods and services identified (E-16). The continuing-operations series is re-based across every year to exclude Cerro Matoso, and the tab preamble states the basis (E-02) | No apparent issue: G-10 requires restatements to be disclosed, and they are, at category level | No apparent issue, baseline (not credited). Restatement disclosure is what the standard requires; publishing the affected sub-lines rather than only the total is good practice within that requirement | No apparent issue · High | The FY2025 comparative a reader uses is the restated one, and the reader can see what moved | Not applicable |
| D2-05 | The methodology discloses that South32's position at several points in the same commodity life cycle produces inherent double counting between Scope 3 categories which "may inflate our reported total Scope 3 emissions", without sizing it (E-40) | Minor limitation: the GHG Protocol categories are designed to be mutually exclusive and the company discloses that for it they are not | Decision-usefulness concern, minor. The disclosed Scope 3 total is stated by the company to be an overstatement of unknown size | Minor limitation · Medium | A reader cannot tell the gross-of-overlap total from the net | An estimate of the overlap, or a net figure beside the gross (F-26) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D3-01 | Dual Scope 2 reporting is applied throughout, on both portfolio bases, and both bases carry the statutory audit opinion on continuing operations (E-01, E-02, E-10). Factor sources are named per operation for both methods (E-42) | No apparent issue | No apparent issue, baseline (not credited). Dual reporting is the GHG Protocol requirement | No apparent issue · High | Both measures of the same electricity are available | Not applicable |
| D3-02 | Location-based Scope 2 fell 16.2% (17.3 to 14.5 MtCO₂e, total operations) in the same year market-based Scope 2 rose 8.0%, closing a gap of 4.0 MtCO₂e to 0.1. Only the market-based movement is narrated, and the narrating sentence does not name its basis (E-01, E-03). The South African location-based factor source moved from the 2022 to the 2023 Grid Emissions Factor Report between periods, and consumption at Mozal fell 31% (E-42, E-18); neither effect is sized | Minor limitation: dual reporting is complete, and there is no requirement to narrate both | Decision-usefulness concern. The largest single feature of this company's Scope 2 position disappeared in one year and no part of the disclosure explains it. A grid emission factor update is not abatement, and a reader cannot tell how much of the fall it is | Decision-usefulness concern · Medium-high | A reader taking the location-based fall as progress would be taking an emission factor update as abatement | Explain the location-based movement and separate the consumption effect from the factor effect (F-11, F-19) |
| D3-03 | Renewable energy fell from 25 to 12.5 PJ, 16% to 9% of consumption on the total-operations basis, on the loss of Cahora Bassa hydroelectric supply to Mozal Aluminium and the Cerro Matoso divestment, partly offset by Worsley biomass nearly doubling (E-18). No certificate-based renewable claim is made | No apparent issue | Decision-usefulness concern, minor. The fall is disclosed in the data book but is not narrated anywhere in the Annual Report, and it is the physical counterpart of the Scope 2 rise the Annual Report does narrate | Minor limitation · High | A reader of the narrative sees the emissions consequence without the energy-mix cause | State the renewable share and its movement in the emissions narrative |
| D3-04 | The FY35 target's central lever remains an affordable low-carbon electricity solution for Hillside Aluminium, which has not been secured. FY2026 activity is a joint working group with Eskom, technical and commercial workshops and a site visit; the nuclear-derived environmental attribute certificate option was not pursued further on treatment uncertainty (E-25, E-26) | Minor limitation | Decision-usefulness concern. The preferred pathway requires multiple gigawatts of renewable supply, substantial grid upgrades and enabling regulation beyond 2031, none of it quantified, costed or dated; the alternative pathway is closure, which the financial statements use as the basis of long-term reporting assumptions | Decision-usefulness concern · High | The dominant delivery risk is described but not sized | A quantified, dated pathway with a stated fallback (F-21) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D4-01 | Eight of fifteen categories are quantified, one is folded into another with a stated reason, two are excluded on a stated materiality assessment, one is inside Scope 1 under the consolidation approach and three are not applicable (E-15, E-40). Each exclusion carries a reason. The total carries voluntary limited assurance (E-11) | No apparent issue | No apparent issue on completeness. OUT-STK-13 tested and not triggered: the categories are itemised on GHG Protocol labels, the residual is small and reasoned, and the total is assured. Category 5 and 12 exclusions rest on assertion rather than a bounding estimate, which is an improvement note | No apparent issue · High | A carbon accountant can see which categories are in and which are out | Bounding estimates for Categories 5 and 12 |
| D4-02 | Value-chain emissions carry no quantitative reduction target. The commitments are engagement objectives, to engage 80% of key suppliers and 80% of key customers by FY2028, reported achieved at over 80% and over 90% (E-20). Scope 3 is 28.6 MtCO₂e, 58% of the combined footprint, and rose 22% (E-19) | Minor limitation: no standard requires a Scope 3 target | Decision-usefulness concern, escalated by materiality and by presentation. Engagement is a process metric and not a reduction (T-SUP-03, T-PROC-05); it is reported as an achievement on the same pages that report the underlying emissions rising by a fifth, and the statement that no quantitative Scope 3 target exists appears in the transition plan rather than in the Annual Report | Decision-usefulness concern · High | More than half the emissions attributable to South32's products sit outside every measurable commitment, and a reader of the Annual Report alone is not told so in terms | A quantified objective for processing of sold products, or a stated influence tonnage and date (F-9) |
| D4-03 | Category 10 rose 50% to 21.8 MtCO₂e on higher alumina sales and the restart of Australia Manganese after cyclone damage, with no change in method (E-15, E-19). Manganese processing rose from 4.3 to 10.8 MtCO₂e against a copper-equivalent production recovery at Australia Manganese from 18 to 48 kt (E-24) | No apparent issue | No apparent issue on attribution. The movement is volume, the company says so, and the prior-year comparability holds because the method did not change. This is the reciprocal of a physical-risk event: the same cyclone that removed the volume in FY2024 returned it in FY2026 | No apparent issue · High | A reader can attribute the Scope 3 rise correctly | Not applicable |
| D4-04 | Downstream processing of zinc and lead concentrates, molybdenum, gold and silver is excluded from Category 10 on a stated but unquantified materiality basis (E-41). The methodology states the exclusion "will be periodically reviewed" | Minor limitation | Decision-usefulness concern, minor. The reason is disclosed and plausible on volumes, and no bounding estimate is given, so the magnitude is cannot-verify. A-21 applies to the stated intention to review: neither a fault nor a credit | Minor limitation · Medium | A reader cannot bound the omitted tonnage | A bounding estimate (F-24) |
| D4-05 | Category 11 moves from 1.5 MtCO₂e to not applicable, on the ground that the company "no longer produces products applicable to category 11" following the August 2024 sale of Illawarra Metallurgical Coal (E-15, E-19) | No apparent issue | No apparent issue. The reclassification is consistent with the portfolio and the reason is stated. It is a portfolio effect, not an abatement, and the company presents it as a year-on-year decrease of 1.5 MtCO₂e rather than as progress | No apparent issue · High | A reader can see the fall is a divestment consequence | Not applicable |
| D4-06 | Scope 3 emissions are prepared on a mix of bases: downstream categories on equity share, upstream on category-specific methods, all inside a total presented alongside operational-control Scope 1 and 2 (E-13, E-40) | Minor limitation: the GHG Protocol permits this and the boundaries table discloses it | Decision-usefulness concern, minor. A combined footprint figure mixes an operational-control numerator with equity-share downstream categories, which the disclosure states but does not flag where the combined figure is used | Minor limitation · Medium | The 49.1 MtCO₂e combined footprint is not on a single consolidation basis | Note the mixed basis wherever a combined footprint is presented |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D5-01 | 79,981 Australian Carbon Credit Units and 100,846 South African offset units were retired in FY2026, itemised by project, vintage, method, serial number range, cancellation date, jurisdiction, registry, transaction purpose and facility, all against regulatory liabilities. None is included in the net emissions calculation, which equals gross (E-30, E-01) | No apparent issue | Genuine positive. Serial-number-level retirement records are above the disclosure baseline and are the evidence a net claim depends on (F-3) | No apparent issue · High | A reader can confirm the reported figure carries no offset | Not applicable |
| D5-02 | The FY35 target's gross reduction is stated equal to its net reduction, with no current planned use of carbon credits, and the company states it has not acquired credits for the purpose (E-06, E-26) | No apparent issue | Genuine positive, qualified. Setting the gross target equal to the net target is a commitment about delivery, not a description. The qualification is that the company states the post-transaction reassessment "may indicate a role for carbon credits" (F-1, and see F-5) | No apparent issue · High | A reader knows the 50% is presently intended to be physical | Not applicable |
| D5-03 | The Australian Safeguard Mechanism excess for FY2025 across the three Australian facilities is 183,312 tCO₂e; the units surrendered against it total 79,981 (E-29, E-30) | Potential compliance concern, low severity and low confidence: the acquittal may be complete through instruments not disclosed, and no non-compliance is inferred (AI-20) | Decision-usefulness concern. A reader cannot close out compliance with the regulation covering 81% of Scope 1 from what is published | Decision-usefulness concern · Low-medium confidence | The compliance position is open on the face of the disclosure | A facility-level acquittal statement (F-13, F-20) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D6-01 | The announced sale would reduce the FY2021 target baseline from 17.5 to about 1.7 MtCO₂e, and the target, the pathways, the assumptions, the initiatives, the governance and the performance measures are all stated to be under review in FY2027 (E-04, E-05). No pro-forma FY2026 position for the residual portfolio is given | No apparent issue: nothing requires a pro-forma recalculation before completion, and the company discloses the intended recalculation trigger (E-07) | Decision-usefulness concern, serious. The reader is given a new starting point roughly a tenth of the current one and no new current figure, so the commitment cannot be sized in either direction. On completion, about 90% of the emissions the target was set over would leave the boundary through a sale rather than through abatement | Decision-usefulness concern · High | The central commitment in the disclosure is presently unmeasurable for the business that will exist | The residual portfolio's FY2026 position beside the pro-forma baseline, and a statement of the target's intended treatment (F-5, F-18) |
| D6-02 | Progress is stated as 20.5 MtCO₂e against a 17.5 MtCO₂e baseline, being a total-operations figure against a continuing-operations adjusted baseline. Like-for-like is 20.2 against 17.5 (E-03, E-04, E-02). The company's boundaries table states the opposite convention (E-13) | Minor limitation | Decision-usefulness concern. A reader reproducing the calculation on matching bases gets 15.4% rather than 17.1%. The direction of the error is unfavourable to the company, which limits the claim-quality concern but not the comparability one | Decision-usefulness concern · High | The most important number in the disclosure cannot be reproduced as printed on matching definitions | State the comparison on continuing operations (F-6) |
| D6-03 | On the target's own basis, emissions rose 4.7% from 19.3 to 20.2 MtCO₂e and are 15.4% above the adjusted baseline in year five of fourteen. The residual reduction required, 56.7% across nine years or about 8.9% a year compounding, is not stated (E-02, E-04) | No apparent issue: no rule requires the arithmetic | Decision-usefulness concern. Every input is published and assured; the reader is left to do the arithmetic that determines whether the target is plausible | Decision-usefulness concern · High | Target feasibility is not presented | Publish the residual reduction and the implied annual rate (F-7) |
| D6-04 | No interim target exists between FY2026 and FY2035, stated in terms in the methodology. What exists are indicative milestones for the maturation of external dependencies at Hillside (E-08) | Minor limitation | Decision-usefulness concern. Nine years with no testable milestone, and the endpoint itself under review | Decision-usefulness concern · High | There is no point at which a reader can test progress against a commitment | A dated interim milestone (F-8) |
| D6-05 | Mozal Aluminium, 19% of operational emissions, was placed on care and maintenance on 15 March 2026, and the methodology states that this did not trigger rebaselining because the operation remains under operational control and inside continuing operations (E-27, E-07) | No apparent issue | No apparent issue. The treatment of a suspended operation in the baseline is stated in terms, which is what the recalculation policy needed to address. Its future is not stated, and it is excluded from the announced sale, which is a live input to the residual-portfolio position (F-18) | No apparent issue · High | A reader knows a suspension does not reset the baseline | State the expected treatment of Mozal in the post-transaction portfolio |
| D6-06 | The target has not been third-party validated and the company states so; it was derived from IPCC 1.5°C reference points and Australia's Nationally Determined Contribution, not from a sectoral decarbonisation approach, which the company also states (E-06, E-09) | No apparent issue | No apparent issue, baseline (not credited). Disclosing the absence of validation is candour, not a positive (A-16), and the absence itself is not a defect where no validation is claimed (T-SBTi-01) | No apparent issue · High | A reader does not mistake the target for a validated one | Not applicable |
| D6-07 | The valuations include the cost and benefit of the identified initiatives necessary to meet the FY35 target; the amount is not disclosed. The 2050 pathway is stated not to be fully defined so its costs are excluded (E-35) | No apparent issue | Decision-usefulness concern, minor. The capital signal cannot be reconciled with the commitment | Minor limitation · High | The provided amount is unknown | Disclose the amount or a range (F-28) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D7-01 | Reasonable assurance is obtained over continuing-operations Scope 1 and both Scope 2 bases under the statutory audit, with an unmodified opinion; governance and strategy carry an unmodified limited-assurance review conclusion; Scope 3 and total energy carry voluntary limited assurance (E-10, E-11) | No apparent issue | No apparent issue, baseline (not credited). The engagement is a statutory one, not a voluntary one: the audit report is addressed to shareholders, is conducted under the Australian Standards on Sustainability Assurance timeline standard, and opines that the disclosures are prepared in accordance with the Corporations Act. The separate engagement over Scope 3 and energy is expressly described as one the Directors "voluntarily requested". Meeting a statutory obligation is baseline (A-16) | No apparent issue · High | The Scope 1 and 2 figures are audited | Not applicable |
| D7-02 | The assured set narrowed. Operational GHG emissions intensity carried limited assurance in the prior period and is in neither FY2026 engagement (E-11), in a year in which it rose 6.6%. The comparatives are expressly outside the audit engagement (E-10). The metric's denominator is published on a different basis from the one the metric uses (E-48) | Minor limitation: nothing requires intensity to be assured | Decision-usefulness concern, minor. The metric that normalises emissions for production is unassured and not reproducible from published figures | Minor limitation · High | A reader cannot check the intensity figure or rely on an opinion over it | Publish the denominator on the metric's own basis and return intensity to the assured set (F-23) |
| D7-03 | The climate element of the long-term incentive vested at 6.5% of a 10% weighting, assessed on studies, pot conversions, trials, a working group and a consortium workstream, in a year in which emissions on the target's basis rose 4.7% (E-38). The annual Business Scorecard contains no greenhouse gas measure, though 35% of its metrics are sustainability-related (E-39) | No apparent issue: no rule requires an emissions metric in incentive design | Decision-usefulness concern. The board rewarded activity while the outcome moved the other way, and the annual incentive that drives behaviour within the year contains no emissions measure at all | Decision-usefulness concern · High | A reader assessing what the board actually rewards finds no emissions outcome in either instrument | An emissions outcome in the long-term incentive and an emissions metric in the scorecard (F-14) |
| D7-04 | The FY35 target is described consistently across the statutory report, the methodology and the transition plan: "halve its net operational emissions by FY35 from FY21 levels" in the financial statements, "Net, 50%. Gross, 50%" in the methodology, "Halve our net operational emissions by FY35 from FY21 levels" in the plan-at-a-glance (E-35, E-06) | No apparent issue | No apparent issue, baseline (not credited). Saying the same thing to every audience is the requirement, not an achievement | No apparent issue · High | A reader gets one description of the commitment | Not applicable |
| D7-05 | Decarbonisation expenditure was US$3.4 million against total capital expenditure of US$1,441 million, a fall of 68% from the prior period. Transition-materials capital expenditure of about US$986 million is reported under the same cross-industry metric heading (E-21, E-22, E-23) | No apparent issue | Decision-usefulness concern. Capital allocation is the most reliable execution signal, and the disclosure places mine development for transition commodities beside decarbonisation spending under one heading, where the first is three hundred times the second | Decision-usefulness concern · High | A reader scanning the climate capital metrics sees a figure that is not decarbonisation capital | Separate the two lines with their own trends, and publish the FY35 capital envelope (F-10) |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D8-01 | The portfolio is described as 100% Transition Materials under the Climate Action 100+ Net Zero Standard for Diversified Mining, with only copper in the key tier at about 10% of copper-equivalent production and the denominator excluding gold and, after divestment, Cerro Matoso (E-24, E-23) | Minor limitation: the classification is applied as the framework defines it and the tiers are published | Decision-usefulness concern. Supplying transition commodities is a market position, not an emissions reduction. Reported as 100% under a climate metric heading, it reads as decarbonisation, and the four commodities in the "other" tier carry over 95% of operational emissions | Decision-usefulness concern · High | A reader takes a portfolio classification for a climate outcome | Present the tiers together with the emissions of the classified commodities (F-15) |
| D8-02 | Two operations carrying 76% of operational emissions are under a binding conditional agreement to be sold; a third carrying 19% is on care and maintenance; the emissions of the retained business are not stated (E-05, E-14, E-27) | No apparent issue | Decision-usefulness concern, serious, and the same concern as D6-01 viewed from the sector side. A mining company's climate position is its asset base, and the asset base is being replaced within the target period | Decision-usefulness concern · High | The disclosure describes a portfolio that will not exist | A pro-forma residual position (F-5, F-18) |
| D8-03 | Real deployed abatement in the year: biomass consumption at Worsley Alumina nearly doubled, stated to contribute a 3% reduction in that operation's Scope 1, and AP3XLE energy efficiency technology reached 66% of Hillside's pots, a further 10 percentage points, with electricity efficiency of 13.51 MWh per tonne of aluminium (E-25, E-38). Two studies progressed and one, waste heat to digestion, was assessed and abandoned as not justifying investment | No apparent issue | Decision-usefulness concern, minor. Named, sized, deployed abatement exists and is small: about 0.1 MtCO₂e against a footprint of 20.5, funded by US$3.4 million. Workable: the reader's action is to identify the named projects and their stated completion percentages; the disclosed data are the AP3XLE percentage, the biomass statement and the spend | Minor limitation · High | A reader can see what was actually deployed and what it cost | Publish expected abatement against each named initiative |
| D8-04 | Non-operated joint ventures are reported at equity share inside Category 15 at 1.4 MtCO₂e, with Brazil Alumina 59%, Brazil Aluminium 27% and Sierra Gorda 14% of the category, and a full equity-share Scope 1 and 2 series is published alongside the operational-control series (E-47, E-01, E-28) | No apparent issue | Decision-usefulness concern, minor. The look-through is quantified but the investees' own targets and headroom are not disclosed, so inherited emissions-growth exposure is neither raised nor sized. Workable: the reader's action is to size the look-through at 1.4 MtCO₂e and treat investee trajectories as unknown; the disclosed data are the equity percentages and the operator-sourced figures. Magnitude of any inherited growth stays cannot-verify (A-05, SEC-INV-LT-17) | Minor limitation · Medium | The joint-venture share is visible; its trajectory is not | Investee target and headroom disclosure |
| D8-05 | The two largest emitting operations are described by exposure type: Hillside is approximately 90% Scope 2 from Eskom electricity, Worsley approximately 99% Scope 1 from process heat (E-25, AR 2026 p.97). Both are quantified as shares of their own operational emissions | No apparent issue | No apparent issue, baseline (not credited). Naming the exposure type per asset is what SEC-MIN-01 expects of a diversified miner | No apparent issue · High | A reader can see which lever applies where | Not applicable |
| D8-06 | Emissions intensity rose 6.6% to 25.9 tCO₂e per tonne of copper-equivalent production, and the methodology states in terms that a reduction in intensity would not necessarily indicate a reduction in absolute emissions (E-01, E-48) | No apparent issue | No apparent issue. The intensity metric is presented with its own limitation stated and the absolute series co-located, which is what T-14 requires. The metric moved adversely and is reported as such | No apparent issue · High | A reader is not offered intensity as a substitute for the absolute trend | Not applicable |
| ID | Finding & evidence chain | Min-compliance | Decision-usefulness / claim-quality | Severity · Confidence | Consequence | What would fix it |
|---|---|---|---|---|---|---|
| D9-01 | Physical risk is assessed at asset level under SSP2-4.5 and SSP5-8.5 using downscaled CMIP6 ensembles from Jupiter Intelligence, carried into life-of-operation plans, valuations and closure provisions, with a Climate Adaptation and Resilience Plan of five initiatives and a Worsley hydrological variability study commenced in FY2026 (E-37) | No apparent issue | No apparent issue. Relevant to the business model and transparent enough to interrogate, which is the N-04 test. The review does not assess modelling quality and says so | No apparent issue · High | A reader can interrogate the method | Not applicable |
| D9-02 | The company's own stated explanation for being above its target baseline is Southern African drought reducing hydroelectric supply, and a cyclone removed and then restored a fifth of value-chain emissions across two years (E-03, E-19). Neither is treated as a quantified physical risk to the target | Minor limitation | Decision-usefulness concern, minor. The realised physical exposure is the dominant driver of the target gap and sits in the emissions narrative rather than in the physical-risk section, where the target sensitivity would be | Minor limitation · High | The link between physical risk and target delivery is not made | State the emissions sensitivity of the target to hydrological supply |
| Base issue | Chains to | Rule + evidence IDs | Escalated severity |
|---|---|---|---|
| The announced sale would cut the target baseline by about 90% (D6-01) | Every target finding, the transition plan, the 2050 goal and the remuneration measure, because the company states each of them is to be reassessed as a consequence. The link is stated by the company, not inferred | T-BASE-01, G-10, T-05, S2-38, GOV-01, YOY-06; E-04, E-05 | Decision-usefulness concern, serious, and the dominant finding in the report |
| The progress statement mixes portfolio bases (D6-02) | The regulator consistency criterion, because the company's own boundaries table states the opposite convention and the audited figures sit on the other basis | T-BASE-01, DR-02, A-01B; E-03, E-04, E-13, E-10 | Decision-usefulness concern; holds the regulator row rather than reading it down, because both bases are published and labelled |
| The narrated figures sit outside the audit scope (D2-02) | The reliability a reader attaches to the headline, because reasonable assurance is the strongest signal in the document and it attaches to different numbers | A-01B, GOV-14, OUT-TB-03; E-01, E-02, E-03, E-10 | Decision-usefulness concern |
| The location-based Scope 2 fall is unexplained while the market-based rise is narrated (D3-02) | The real-versus-accounting test, because a grid emission factor update presented without explanation can be read as abatement | S2-28, A-19, G-BAU, G-10; E-01, E-03, E-42 | Decision-usefulness concern; the split stays cannot-verify (F-19) |
| Value-chain emissions rose 22% under engagement objectives reported as exceeded (D4-02) | The retail and public reader-impression criteria, because a section reporting its objectives met sits directly above the figures showing the emissions it addresses rising by a fifth | T-SUP-03, T-PROC-05, OUT-TB-02, S3-25; E-19, E-20 | Decision-usefulness concern, and the criterion that defeats R2 |
| Decarbonisation expenditure of US$3.4 million against US$1,441 million of capital expenditure (D7-05) | Target feasibility and the public evidenced-action criterion, because the required rate is about 8.9% a year and the capital signal does not support it, and because transition-materials capital sits under the same heading | T-06, S2-35, SEC-MIN-04, OUT-TB-02; E-21, E-22, E-23 | Decision-usefulness concern; the FY35 capital envelope stays cannot-verify (F-28) |
| The FY2025 Safeguard exceedance is only 44% acquitted on the face of the disclosure (D5-03) | The regulator standards criterion, because it concerns the scheme covering 81% of Scope 1. It does not escalate to an allegation: instruments not disclosed may complete the acquittal (AI-20) | DR-05, A-01C, SEC-MIN-11, A-05; E-29, E-30, E-49 | Potential compliance concern, low confidence; recorded as cannot-verify (F-20) |
| Biogenic carbon dioxide moved inside Scope 1 (D2-03) | The Scope 1 series comparability and, through it, the reading of the year's one real abatement, because more biomass lowers fossil Scope 1 and raises the biogenic figure now inside it | GHG-STD-05, G-10, GHG-STD-08; E-17, E-25 | Minor limitation; does not escalate |
| Screen | Output | Basis |
|---|---|---|
| Required Interventions Schedule | Potentially applicable; evidence required | Steam electrification and low-carbon calcination at Worsley Alumina, pot-line efficiency at Hillside, and the Hillside electricity supply solution are the interventions a schedule would prescribe for this footprint. The company is progressing the first three and has a working group on the fourth, without dates, expected abatement or capital attached (E-25, E-26), which is the evidence a schedule would need. |
| Clean Alternative Assessment | Potentially applicable; evidence required | Two options were investigated and set aside in FY2026 with reasons stated but not evidenced against a formal assessment: waste heat to digestion at Worsley, rejected because capital intensity and expected reduction did not justify investment, and Eskom's nuclear-derived environmental attribute certificates, not pursued on treatment uncertainty under the EU CBAM (E-38, E-25). A clean alternative assessment would record each option, its cost and its ground of rejection. |
| Prohibited Activities Schedule | Not apparently applicable | Energy coal and metallurgical coal are out of the portfolio. No prohibited activity is identified from reviewed materials. |
| Rule family | Applied? | Result |
|---|---|---|
| Applicability gate (L / S2-01..06) | Yes | First mandatory AASB S2 period. Statements prepared under ss.296A, 296C and 296D with a Directors' declaration and unmodified opinion and conclusion. Transitional reliefs applied and disclosed (D1-01, D1-02). One production defect in a statutory document (D1-03). |
| GHG inventory foundation (G / GHG-STD) | Yes | Boundary disclosed on operational-control and equity-share bases with a mapping table; five coexisting FY2026 totals, each labelled and reconciling (D2-02); biogenic reclassification without restatement (D2-03); prior-year Scope 3 restatement disclosed at category level (D2-04); acknowledged inter-category double count unsized (D2-05). |
| Scope 1 (G-06 / S2-26) | Yes | Decomposed by source, gas, operation and asset across five years; no combined-only figure. Baseline practice, not credited (D2-01). |
| Scope 2 & renewables (E / S2-28) | Yes | Dual reporting applied throughout and both bases audited on continuing operations (D3-01). The unexplained location-based fall is the year's principal Scope 2 finding (D3-02). Renewable share halved without narration (D3-03). No certificate-based renewable claim. |
| Scope 3 (S3 / S3A / G-15) | Yes | Eight categories quantified with the balance reasoned; OUT-STK-13 tested and not triggered (D4-01). No quantitative target over 58% of the footprint (D4-02). Category 10 rise is volume, not method (D4-03). Commodity exclusion unsized (D4-04). |
| Offsets / net claims (E-08..22 / G-11) | Yes | Serial-number-level retirement register; no credits in the net figure; gross target equals net target (D5-01, D5-02). Safeguard acquittal unreconciled (D5-03). |
| Targets & transition (T / S2-14/15/40) | Yes | Seven findings: the pending baseline collapse, the mixed-basis progress statement, the unstated residual reduction, the absent interim target, the care-and-maintenance treatment, the validation position and the undisclosed capital envelope (D6-01 to D6-07). |
| Governance / remuneration / assurance (GOV / A-11) | Yes | Statutory assurance obtained and not credited as above baseline (D7-01); assured set narrowed (D7-02); activity-based incentive vesting against a rising metric and no scorecard emissions measure (D7-03); one consistent target description (D7-04); decarbonisation capital (D7-05). |
| Sector (SEC-*) | Yes | Mining and metals module. SEC-MIN-01, -04, -05, -06, -07, -08, -09, -11 and -12 all fired (D8-01 to D8-06, D3-04, D6-04). |
| SEC-FI-TGT-04 | No | Not a financial institution. |
| SEC-FI-05A | No | Not a financial institution. |
| SEC-SF / SEC-INV-LT | Partly | Non-operated joint ventures reported at equity share in Category 15 with operator-provided data and named shares (D8-04). Investee target headroom not disclosed, so inherited growth exposure is not quantified: I5 partial. SEC-SF-11 fired on the FY2021 baseline year dropping out of the published series. |
| G-20 (boundary reach) | Yes | Applied to the non-operated joint ventures and to Mozal Aluminium on care and maintenance. Mozal remains under operational control and inside Scope 1 and 2; the non-operated ventures fall outside operational control and are reported in Scope 3 Category 15, which is the correct treatment, not an exclusion. |
| OUT-TB-21 (bounded completeness words) | Yes | Applied to "Our FY35 target covers 100% of our operational emissions" (bounded on its face to operational emissions, and true) and to "These Transition Materials represent 100% of our portfolio on a copper equivalent basis" (bounded to a stated denominator, and the concern is the framing, not the arithmetic: D8-01). |
| A-21 (disclosed intention to review) | Yes | Applied to the stated intentions to review the Category 5, 8, 10 and 12 assessments, to prepare Scope 3 under the standard, and to reassess the FY35 target in FY2027. None is treated as evidence the present treatment is wrong; none is credited. The FY2027 reassessment bears on the recommendation, not on the finding, which rests on the unpublished residual position. |
| NOCO2-MAP-01/02 | Yes | Clause-level mapping at §6.1; §6.1 populated from it. |
| Nature / physical risk (N) | Yes | Physical-risk assessment relevant and transparent (D9-01); the realised hydrological exposure is not linked to target delivery (D9-02). |
| Disclosure risk (DR-01..07 / A-01C) | Yes | Cross-source matrix at Annex J. NGER reconciliation clean for FY2024-25 to 61 tonnes on 3.48 million; FY2026 register not yet published. |
| Year-over-year (YOY-01..08) | Yes | Five periods and four report types available. Trajectory at §3.4, register at Annex K. |
| Ref | Item requested | Why needed | Rule ID | Status |
|---|---|---|---|---|
| K-01 | Pro-forma FY2026 operational emissions for the portfolio retained after the announced sale, on the same basis as the 1.7 MtCO₂e pro-forma baseline, and the expected treatment of Mozal Aluminium | Without it the central commitment cannot be sized for the business that will exist | T-BASE-01, G-10 | Open (F-18) |
| K-02 | The tonnage of the FY2026 location-based Scope 2 movement attributable to lower consumption and to the change in the South African grid emission factor source | A factor update is not abatement, and the fall is 2.8 MtCO₂e | S2-28, A-19, G-10 | Open (F-19) |
| K-03 | A facility-level statement of how the FY2025 Safeguard Mechanism excess of 183,312 tCO₂e was acquitted, and with what instruments | 79,981 units are disclosed against it | DR-05, A-01C | Open (F-20) |
| K-04 | Expected abatement, capital cost and date for each step of the FY35 pathway at Worsley Alumina and Hillside Aluminium | The pathways are described without quantum | T-DEP-04, T-06 | Open (F-21) |
| K-05 | The calculation behind "approximately 10%" for the Worsley boiler conversion, and the FY2021 asset-level figure it is measured against | The asset series begins in FY2022 in the current data book | A-19, SEC-MIN-12 | Open (F-22) |
| K-06 | Copper-equivalent production on the operational-control 100% basis that the emissions intensity metric uses | The published copper-equivalent figures are on an equity-share basis, so the metric cannot be reproduced | T-14, S2-29 | Open (F-23) |
| K-07 | A bounding estimate for downstream processing emissions from zinc and lead concentrates, molybdenum, gold and silver | The exclusion is reasoned but unsized | S3-25, A-05 | Open (F-24) |
| K-08 | FY2026 Safeguard Mechanism baselines and covered emissions, and the FY2026 NGER register entry | The submission period closes 31 October 2026 | A-01C, DR-05 | Open, timing (F-25) |
| K-09 | An estimate of the double count the company acknowledges between Scope 3 categories | The company states the total may be inflated by an unknown amount | S3-25, GHG-STD-08 | Open (F-26) |
| K-10 | The count of key suppliers and the volume of product sold that the 80% and 90% engagement figures are measured against | The measures are defined but the denominators are not published | T-COV-02, T-PROC-05 | Open (F-27) |
| K-11 | The capital amount for the FY35 initiatives included in the Group's valuations | The financial statements state the amount is included without disclosing it | T-06, S2-35 | Open (F-28) |
| K-12 | An estimated EU Carbon Border Adjustment Mechanism exposure once the first reporting period closes, with the tonnage and assumed rate | Aluminium exports to Europe are the exposed flow and the mechanism took effect 1 January 2026 | S2-33 to S2-37 | Open, timing (F-29) |
| K-13 | The Sustainability Standards and Frameworks Index 2026 | To test the TCFD, SASB and Climate Action 100+ mapping the company asserts | S2-01 to S2-06, C-SBTi-02 | Open, document not provided |
| Trigger detected | Scans run | Sections loaded | Outcome |
|---|---|---|---|
| Net zero goal (2050, operational and all-scopes) | Target boundary, transition plan, Scope 1/2/3, gross versus net, residual emissions, offsets, assurance scope, prior claims, reader-burden caveats | 10, 11, 03 | The 2050 position is expressly a goal with no identified pathway, and the company states it will review the pathway in light of the sale. Cannot verify by construction; not a claim defect (C-14) |
| Target achievement / on-track language | Boundary, baseline, current-year, progress calculation, gross versus net, offsets, Scope 3 coverage, method changes, mergers and acquisitions, restatements, assurance, remuneration links | 11 | F-5 to F-8, F-14; D6-01 to D6-07, D7-03 |
| Combined "Scope 1 and 2" figures throughout | Decomposition into Scope 1 and Scope 2, and Scope 2 into location and market-based, on both portfolio definitions | 06, 07, 08 | Fully decomposable from published data. The decomposition is what produces F-11, because the two Scope 2 bases moved in opposite directions |
| Market-based Scope 2 as the target's measurement basis | Location versus market-based, consumption, contractual instruments, residual mix, factor sources | 08 | D3-01, D3-02; the South African location-based factor source changed between periods (E-42) |
| Scope 3 disclosed with categories excluded | Category coverage, business-model-obvious categories, exclusions, data quality, spend versus supplier-specific, target boundary, consistency | 09 | D4-01 to D4-06; OUT-STK-13 tested and not triggered |
| Coverage percentage claims ("100% of operational emissions", "100% Transition Materials", "80% of key suppliers") | Numerator, denominator, excluded categories | 11, 09 | C-05, C-06, C-07; F-9, F-15; F-27 |
| Supplier and customer engagement metrics | Engagement versus reduction; process versus performance; measured trajectory | 09, 03 | F-9; the engagement objectives are reported exceeded while the underlying emissions rose 22% |
| Method, boundary, factor, base-year and restatement changes | Time-series comparability, baseline recalculation, target progress, real versus accounting, mergers and acquisitions, peer comparability | 06, 11 | D2-03, D2-04; the Scope 3 restatement is disclosed at category level, the biogenic change is not restated |
| Externally dependent target | Target year versus dependency pathway, disclosed bridge, fallback actions | 11 | D3-04; the alternative pathway is closure in 2031 and underpins financial reporting assumptions |
| Any reduction or target-progress claim | Business-as-usual decomposition: grid factor versus consumption versus contractual instruments; portfolio versus abatement | 06, 03 | §3.3; the year's identified abatement is about 0.1 MtCO₂e |
| Australian entity; metrics appearing in more than one place | NGER register lookup and cross-source consistency matrix | 16, 01 | Annex J; reconciles to 61 tonnes on 3.48 million for FY2024-25 |
| More than one reporting period and report type | Multi-period series across five years and four report types, from the earliest available period up to FY2026 | 17, 06, 11 | §3.4, Annex K |
| Assurance statements (two engagements) | Subject matter, level, assured metrics, exclusions, qualifications, whether nearby claims imply broader assurance | 12 | D7-01, D7-02, F-12; the narrated figures are outside the audited set |
| Climate-linked remuneration | Metric boundary, gross versus net, Scope 3 inclusion, offsets, target progress, assurance, controls | 12 | D7-03, F-14 |
| Sources contracted, operated or controlled by another party | G-20 which-scope test on the non-operated joint ventures and on Mozal Aluminium under care and maintenance | 06, 09 | Both correctly treated: joint ventures outside operational control sit in Category 15; Mozal remains inside Scope 1 and 2. Not exclusions |
| Completeness words beside named quantities | OUT-TB-21 applied to "100% of our operational emissions" and "100% of our portfolio on a copper equivalent basis" | 02 | Both bounded on their face; the concern on the second is placement (F-15) |
| Disclosed intentions to review, extend or improve | A-21 applied to the Category 5, 8, 10 and 12 review statements, the Scope 3 preparation statement and the FY2027 target reassessment | 03, 17 | None treated as a fault; none credited |
| Transition plan / low-carbon opportunity | Actions, capital, dependencies, milestones, Scope 3 coverage, scenario analysis, financial effects, delivery risk | 11 | F-10, F-21, F-28; two options assessed and set aside in the year |
| PCAF / financed emissions | Not run | 13 | Not applicable: not a financial institution |
O.1 NGER reconciliation (A-01C)
| Item | Register (FY2024-25, as at 27/02/2026) | Disclosure | Normalisation applied | Result |
|---|---|---|---|---|
| Scope 1, Australian operations | 3,476,916 tCO₂e | Safeguard covered Scope 1 for FY2025: Worsley Alumina 3,218,588, Groote Eylandt 135,299, Cannington 122,968, totalling 3,476,855 | Operational control, Australian facilities, financial year, Scope 1 only | Reconciles. Residual 61 tonnes, 0.002% |
| Scope 2 location-based, Australian operations | 28,306 tCO₂e | Australian operations' Scope 2 is reported as 0.0 MtCO₂e at one decimal place across Australia Manganese, Cannington and Worsley Alumina | Rounding: 28,306 tonnes is 0.03 MtCO₂e | Consistent within the published precision |
| Net energy, Australian operations | 52,156,288 GJ, or 52.2 PJ | FY2025 energy use for the three Australian operations totals 52.3 PJ | Same three facilities, same year | Reconciles within rounding |
| FY2026 position | Not published | Not testable | The company states the FY2026 submission period runs to 31 October 2026 and the regulator will publish afterwards | Cannot verify for the reviewed period (F-25) |
O.2 Cross-source consistency matrix (DR-02)
| Claim / metric | Annual Report (statutory) | Methodology 2026 | Databook 2026 | Transition plan (CCAP 2025) | Consistent after normalisation? |
|---|---|---|---|---|---|
| FY35 target description | "halve its net operational emissions by FY35 from FY21 levels" (Financial Report note 2(c)); "Halve our net operational emissions by FY35 from FY21 levels" (p.80) | "Reduction: Net, 50%. Gross, 50% (no current planned use of carbon credits)" | Not stated | "Halve our net operational emissions by FY35 from FY21 levels" | Yes |
| FY2026 operational emissions | 20.5 MtCO₂e narrated (p.82); 20.5 and 20.7 total operations, 20.2 and 20.3 continuing, tabulated (p.105); 5.9 / 14.3 / 14.4 audited (p.111) | Not stated | 20.5 total operations market-based; 20.2 continuing market-based; 19.9 equity share | Not applicable | Reconcilable, and all bases are labelled. The divergence is that the narrated figure is not the audited one |
| Target baseline | 17.5 MtCO₂e adjusted (p.83); pro-forma 1.7 MtCO₂e (p.83) | 17.5 MtCO₂e adjusted, with the five divestments listed | Not stated | 18.2 MtCO₂e adjusted, moving to 17.5 after the Cerro Matoso sale | Yes. The plan predates the December 2025 divestment and states the transition to 17.5 |
| Scope 2 movement | "increased 8% (1.1 Mt CO2-e)", basis unnamed (p.82) | Both methods described with factor sources | Market-based 13.3 to 14.4; location-based 17.3 to 14.5 | Not applicable | Reconcilable from the tables. The narrated sentence and the tabulated location-based series move in opposite directions |
| Scope 3 total | 28.6 MtCO₂e (p.86), limited assurance (p.114) | Category methods and exclusions | 28.6 total operations; 28.5 continuing | Not applicable | Yes |
| Decarbonisation expenditure | US$3.4 million (p.87 and p.97) | Not stated | Not stated | Not applicable | Yes, stated twice identically |
| Scope 3 reduction target | Not stated in terms; engagement objectives presented (p.87) | Not stated | Not stated | "we have not established quantitative reduction targets for Scope 3 emissions" | Consistent in substance. The express statement sits only in the transition plan, which is a reader-burden point rather than a divergence |
| Assurance scope | Audit over continuing-operations Scope 1 and both Scope 2 bases; review over governance and strategy; limited assurance over Scope 3 and total energy | "We obtain reasonable assurance over our externally reported performance against the target" | Notes non-operated joint ventures outside the reasonable assurance opinion | Not applicable | Reconcilable. The methodology's assurance sentence is broader than the audit opinion's scope, which covers the emissions figures rather than the progress statement |
O.3 Disclosure-risk register
| Ref | Lens | Exposure | Confidence | Driver | Linked findings |
|---|---|---|---|---|---|
| O-01 | Legal | Low to moderate | Medium-high | The FY35 target appears unqualified in the plan-at-a-glance while the pages either side disclose the sale and its effect on the baseline | F-5; E-04, E-05 |
| O-02 | Legal | Low | High | The progress statement mixes portfolio bases, in the direction unfavourable to the company | F-6; E-03, E-13 |
| O-03 | Regulatory | Moderate | High | The narrated figures sit outside the statutory audit scope inside a document carrying a Directors' declaration | F-12; E-03, E-10 |
| O-04 | Regulatory | Low to moderate | Low-medium | The FY2025 Safeguard excess of 183,312 tCO₂e is 44% acquitted on the face of the disclosure. No non-compliance is inferred; instruments not disclosed may complete it | F-13; E-29, E-30 |
| O-05 | Regulatory | Low | High | Two unresolved page-reference placeholders in a statutory document | F-17; E-43 |
| O-06 | Technology | High | High | The alumina electrification route is technically feasible and commercially blocked; the aluminium electricity solution has not been found | D3-04, F-21; E-25, E-26 |
| O-07 | Physical | Moderate | High | The company's own stated explanation for being above baseline is drought; the emissions sensitivity of the target to hydrological supply is not stated | D9-02; E-03 |
| O-08 | Commercial | High | High | Operations carrying 95% of operational emissions are being sold or are on care and maintenance, and the climate architecture is stated to be under review as a result | F-5, D8-02; E-05, E-27 |
| O-09 | Reader impression | Moderate | Medium-high | Transition-materials classification and transition-materials capital both presented under climate metric headings | F-10, F-15; E-23, E-24 |
P.1 Longitudinal series. Total operations basis (Table A) unless marked. All figures MtCO₂e as published in the FY2026 suite; FY2025 Scope 3 is the restated figure.
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
| Scope 1 | 10.1 | 10.3 | 9.4 | 7.4 | 6.2 |
| Scope 2, market-based | 11.9 | 11.4 | 10.9 | 13.3 | 14.4 |
| Scope 2, location-based | 20.7 | 19.7 | 18.0 | 17.3 | 14.5 |
| Total Scope 1 and 2, market-based | 22.0 | 21.7 | 20.3 | 20.7 | 20.5 |
| Scope 3 | 67.4 | 65.0 | 54.2 | 23.5 | 28.6 |
| Scope 1, continuing operations | 6.6 | 6.8 | 6.6 | 6.3 | 5.9 |
| Scope 2 market-based, continuing operations | 11.3 | 10.9 | 10.5 | 13.1 | 14.3 |
| Scope 2 location-based, continuing operations | 20.1 | 19.1 | 17.5 | 17.1 | 14.4 |
| Total Scope 1 and 2 market-based, continuing operations | 17.9 | 17.7 | 17.0 | 19.3 | 20.2 |
| Scope 3, continuing operations | 47.3 | 45.0 | 40.1 | 21.6 | 28.5 |
| Scope 3 C1 (incl. capital goods), total operations | 4.7 | 6.4 | 1.8 | 3.6 | 2.8 |
| Scope 3 C3, total operations | 0.9 | 1.0 | 1.7 | 1.6 | 1.5 |
| Scope 3 C4, total operations | 1.9 | 1.5 | 0.8 | 0.8 | 0.9 |
| Scope 3 C9, total operations | Not calculated | 0.4 | 0.3 | 0.2 | 0.1 |
| Scope 3 C10, total operations | 40.9 | 37.2 | 35.0 | 14.5 | 21.8 |
| Scope 3 C11, total operations | 18.0 | 17.2 | 13.2 | 1.5 | Not applicable |
| Scope 3 C15, total operations | 1.0 | 1.3 | 1.3 | 1.4 | 1.4 |
| Emissions intensity (tCO₂e per tonne CuEq) | Not reported | 20.4 | 20.6 | 24.3 | 25.9 |
| Total energy use (PJ), total operations | 162 | 160 | 156 | 159 | 137.9 |
| Renewable energy (PJ), total operations | 33 | 33 | 30 | 25 | 12.5 |
| Renewable share of energy | 20% | 21% | 19% | 16% | 9% |
| Scope 1 covered by an emissions-limiting regulation | Not reported | 79% | 76% | 74% | 81% |
P.2 Cross-period tracking register.
| Item tracked | Rule chain | Observation across periods | Normalisation applied | Outcome |
|---|---|---|---|---|
| Direction of travel on the target's own basis | A-19 / G-BAU / GHG-STD-08 | Continuing-operations Scope 1 and 2 market-based: 17.9, 17.7, 17.0, 19.3, 20.2. Up 12.8% across five periods and 4.7% in the reviewed year, against an adjusted FY2021 baseline of 17.5 | Continuing-operations basis consistently re-based to the FY2026 portfolio across all years by the company | Real: an increase, driven by the Eskom emission factor and hydrological supply loss, not by an accounting change. Feeds F-7 |
| Silent restatement / baseline rebasing | G-10 / T-BASE-01 | FY2025 Scope 3 restated 22.7 to 23.5 with Categories 1 and 4 quantified and the reason stated. Continuing-operations series re-based for the Cerro Matoso divestment across every year, disclosed in the tab preamble. Target baseline moved 18.2 to 17.5 for the same divestment, disclosed | Both restatements checked against the prior-period publications | No silent restatement. Both are disclosed and quantified. Feeds D2-04 |
| Dropped disclosures | SEC-SF-11 | FY2021 is no longer carried in any published series: both Table A and Table B run FY2022 to FY2026 on a rolling five-year window, and the target baseline year is therefore off every series and every chart. Emissions intensity left the assurance scope. The Category 10 alumina and manganese sub-splits, first published for FY2024, continue | Rolling-window effect distinguished from deliberate removal | Two dropped items, both consequential: the baseline year and the intensity assurance. Feeds §3.4, D7-02 |
| Dropped disclosures, checked and not sustained | SEC-SF-11 / YOY-04 | The FY2025 financial statements stated that Hillside Aluminium "would be uncompetitive in the Accelerated Transition scenario without an affordable source of low-carbon energy by mid-2030s". That sentence does not appear in FY2026 | Compared like for like against the FY2026 note and the FY2026 climate section | Not a dropped disclosure. The FY2026 note states the life-of-operation plan is limited to 2031 and its extension is highly dependent on affordable low-carbon energy, and the climate section states that closing the smelter in 2031 was the alternative pathway and underpins long-term financial reporting assumptions. Replaced by a more concrete statement. Ruling at L-05 |
| Target weakening or retirement | S2-41 / T-14 / A-18 | FY2025: the target was described as net, with the company recording that offsetting had not been anticipated when it was set and no cap disclosed. FY2026: gross reduction stated equal to net, no credits acquired for the purpose, and neither pathway expected to require them | Compared the FY2025 methodology target table with the FY2026 one | A strengthening, and a substantive one. Credited at F-1. The counterweight is that the baseline itself is about to change (F-5), which is a different mechanism |
| Certification-chain continuity | E-25 / A-18 | No certification is held or claimed in either period | Not applicable | Not applicable |
| Cross-report-type divergence over time | DR-02 / A-01B | FY2025 carried a divergence between the audited remuneration report's description of the target and the plan's. FY2026 carries one description across the statutory report, the methodology and the plan | Compared the four document types in each period | Resolved. A new divergence of a different kind appears inside a single document, between the audited and the narrated bases (F-12) |
| Method changes and comparability | G-10 / GHG-STD-08 | FY2025 changed the Category 10 alumina factors without restating prior years. FY2026 makes no Category 10 method change, so the 50% rise is volume. FY2026 moves biogenic carbon dioxide inside Scope 1 without restating prior years | Each change checked against the prior period's stated method | One new comparability break, small and disclosed (F-16). The prior Category 10 break is now two years old and the affected series has moved past it |
| Physical-risk realisation | N-01 to N-03 | Tropical Cyclone Megan suppressed Australia Manganese production from FY2024, and the FY2026 restart returned manganese processing emissions from 4.3 to 10.8 MtCO₂e. Southern African drought moved Mozal's electricity emissions from 0.0 in FY2024 to 2.4 in FY2025 and 3.1 in FY2026, and is the company's stated reason for being above its target baseline | Volume and factor effects separated where the company sizes them | Both are realised physical exposures with direct emissions consequences, disclosed as operational events rather than as physical-risk outcomes. Feeds D9-02 |
| Structural change | T-BASE-01 / G-10 | Illawarra Metallurgical Coal sold August 2024; Metalloys June 2025; Cerro Matoso 1 December 2025; Mozal Aluminium on care and maintenance 15 March 2026; aluminium value chain under binding conditional agreement from 1 July 2026 | Each traced to its baseline treatment | Four of the five have a stated baseline treatment. The fifth, the announced sale, is stated to be pending recalculation, which is F-5 |
| Assurance trajectory | GOV-14 / A-11 | FY2025: voluntary reasonable assurance over total-operations Scope 1 and 2 on both bases; limited over Scope 3, energy and intensity. FY2026: statutory audit over continuing-operations Scope 1 and both Scope 2 bases; statutory review over governance and strategy; voluntary limited over Scope 3 and energy | Compared the assured item lists directly | Deepened in status and narrowed in content. Intensity left the assured set and the comparatives are expressly excluded. Feeds D7-02 |
| Decarbonisation capital | T-06 / SEC-MIN-04 | US$10.6 million in FY2025 against US$1,353 million of capital expenditure; US$3.4 million in FY2026 against US$1,441 million | Same definition, stated by the company in both periods | A fall of 68% in absolute terms and from 0.78% to 0.24% of capital expenditure. Feeds F-10 |
| Value-chain commitments | T-SUP-03 / T-PROC-05 / YOY-05 | The FY2028 objectives to engage 80% of key suppliers and 80% of key customers, set in the 2025 plan, are reported achieved at over 80% and over 90% in FY2026, two years early, on denominators that remain unpublished. Value-chain emissions rose 22% over the same period | Denominators compared across periods: the customer measure moved from "cannot be defined publicly" to "quantity of product sold" | The measure is now defined, which is an improvement; the denominator is still not published, and the objectives are process metrics reported as achievement against rising emissions. Feeds F-9, F-27 |
*Prepared under the Climate Disclosure Review Rules v15.23 (controlled AI-assisted review). The body (§1–§7) states the verdict and may be issued on its own; the annexes are the working layer. General information only: not legal, financial or investment advice, an audit, an assurance opinion, or a NoCO2 certification or conformance determination. © Carbon Reduction Institute Pty Ltd, ABN 26 122 969 233.*
Each audience score is built from a fixed set of load-bearing criteria, marked before the score is set. "Partial" means the criterion is satisfied only with reader effort that this audience can reasonably spend, not a soft failure. The count matters as well as the score: a score can reach its floor on two failed criteria, so two reports sharing a score may sit some distance apart on the detail below.
| # | Audience | Criterion | Verdict | Why |
|---|---|---|---|---|
| A1 | Carbon accounting | No material category excluded | Pass | Eight of fifteen Scope 3 categories quantified and itemised on GHG Protocol labels; Category 2 folded into Category 1 with a stated reason; Category 8 inside Scope 1 under operational control; Categories 5 and 12 excluded on a stated materiality assessment; Categories 11, 13 and 14 not applicable with reasons. Scope 1 and Scope 2 complete on both bases and both portfolios. Not a trigger for the OUT-STK-13 cap: material sources are itemised, cleanly mappable, the residual is small and reasoned, and the total carries limited assurance |
| A2 | Carbon accounting | Single reconcilable footprint | Partial | Five FY2026 Scope 1 and 2 totals coexist across two portfolio definitions, two Scope 2 bases and two consolidation approaches, and the figure the narrative uses is not the figure the audit opinion covers. Workable: the reader's action is to take the operational-control, market-based continuing-operations total of 20.2 MtCO₂e as the audited footprint and 20.5 as the narrated one; the disclosed data are the labelled page 105 tables, the equity-share table and the organisational boundaries table that maps each basis to its use. Each total reconciles internally and none competes unlabelled for the same slot |
| A3 | Carbon accounting | Method, boundary and version transparency | Pass | A dedicated methodology document states the calculation basis, inputs, assumptions, exclusions and emission-factor source for every Scope 1, 2 and 3 category, the boundary approach, the recalculation triggers with a 5% variance threshold and the full FY35 target definition, and is named in the audit opinion. The organisational boundaries table maps every disclosure to its boundary and presentation basis. The biogenic method change and the prior-year Scope 3 restatement are both stated and quantified. The two unresolved page-reference placeholders are a production defect in the document, not an opacity in the method, and are recorded as F-17 |
| A4 | Carbon accounting | Granularity and assurance sufficient to lift | Pass | FY2026 is liftable at asset, source and gas level, with reasonable assurance over continuing-operations Scope 1 and both Scope 2 bases and limited assurance over the Scope 3 total. The series is liftable too: fifteen Scope 3 categories for five years on both portfolio bases, the continuing basis consistently re-based across every year, and the one restatement quantified line by line. The residual breaks are small and stated: 0.09 MtCO₂e of biogenic carbon dioxide moved inside Scope 1 without restatement, and the comparatives sit outside the audit engagement |
| I1 | Institutional investors | Physical risk relevant and transparent (N-04) | Pass | Asset-level assessment under SSP2-4.5 and SSP5-8.5 on downscaled CMIP6 ensembles from a named provider, carried into life-of-operation plans, valuations and closure and rehabilitation provisions, with a five-initiative adaptation plan and a site-specific hydrological study commenced. Method disclosed sufficiently to interrogate; the review does not assess modelling quality |
| I2 | Institutional investors | Transition risk: derivable target headroom | Partial | The target is absolute, the adjusted baseline is stated at 17.5 MtCO₂e, the current position is published on both bases, the gross reduction is stated equal to the net reduction, the recalculation triggers carry a quantified threshold and the treatment of a suspended operation is stated. Headroom for the portfolio as it stands is therefore derivable. Headroom for the portfolio that will exist is not: the pro-forma baseline of about 1.7 MtCO₂e is published without a corresponding current figure. Workable: the reader's action is to compute the present headroom as 20.2 against 17.5 and to treat the post-transaction target as suspended pending the stated FY2027 reassessment; the disclosed data are the continuing-operations series, the adjusted baseline, the pro-forma baseline and the company's statement of what it will reassess |
| I3 | Institutional investors | Target achievement: real reductions, honest progress | Partial | Progress is stated on the page: the company reports being 17.1% above the FY2021 baseline in the same sentence as the year's 1.0% fall, and attributes the Scope 1 fall to divestment and closure and the Scope 2 rise to Eskom supply and its emission factor. What is not stated is the position on the target's own continuing-operations basis, where emissions rose 4.7%, or the residual reduction required. The year contains about 0.1 MtCO₂e of identified abatement. Workable: the reader's action is to take the continuing-operations series from the data book against the stated baseline and compute the required rate; the disclosed data are the five-year Table B series, the 17.5 baseline and the company's own driver attribution |
| I4 | Institutional investors | Portfolio / financed-emissions completeness | Pass | Not a financial institution, so the analogue applies: non-operated joint ventures are reported at equity share in Category 15 using operator-provided data, with Brazil Alumina, Brazil Aluminium and Sierra Gorda named, their equity shares given and their contribution split by percentage, and a full equity-share Scope 1 and 2 series is published alongside the operational-control series |
| I5 | Institutional investors | Flow-through / look-through exposure | Partial | Category 15 is 1.4 MtCO₂e on the investment-specific method with operator data and a named percentage split. The investees' own targets and headroom are not disclosed, so inherited emissions-growth exposure is neither raised nor quantified; the Category 10 dependence on customer smelter decarbonisation is described qualitatively through the engagement programme. Workable: the reader's action is to size the look-through at 1.4 MtCO₂e and treat investee trajectories as unknown; the disclosed data are the equity percentages, the operator-sourced figures and the named ventures. Magnitude of any inherited growth stays cannot-verify |
| I6 | Institutional investors | Reconstructability by a sophisticated reader | Partial | The material position is reconstructable: the continuing-operations series, the adjusted baseline, the driver attribution, the Scope 3 category series and the assurance scopes are all published. Four things are not: the residual portfolio's position after the sale, the split of the location-based Scope 2 fall, the Safeguard acquittal and the FY35 capital envelope. Workable: the reader's action is to derive the target-basis position and required rate from Table B against the stated baseline and to treat the post-transaction position as an open item; the disclosed data are the five-year dual-basis series and the pro-forma baseline |
| R1 | Retail investors | Headline matches evidence without cross-document work | Partial | The reader meets a single sentence carrying the year's figure, the year-on-year movement and the position against the target baseline, with the drivers named immediately beneath and the closure of one smelter, the 2031 electricity contract at another and the announced sale within four pages. Against that, the chart beside the sentence is drawn on the other portfolio basis, begins in FY2022 so the baseline year is off it, and the 20.5 figure is compared against a baseline adjusted on a different definition. Under OUT-STK-05 the correction is co-located and legible, which is the condition for a 2 rather than a 1. Workable: the reader's action is to read the sentence, which states the position against the baseline in terms; the disclosed data are that sentence and the page 105 dual-basis tables |
| R2 | Retail investors | Targets cover material sources; achievement honest | Not met | Two limbs of one criterion. Coverage: the FY35 target covers 100% of operational emissions, but Scope 3, at 28.6 MtCO₂e of a 49.1 MtCO₂e combined footprint, carries no quantitative reduction target, its largest category is 44% of the whole footprint, and the statement that no such target exists appears in the transition plan rather than in the Annual Report the retail reader holds. What the Annual Report presents instead are engagement objectives, reported exceeded two years early, on the same spread that reports the underlying emissions rising 22%. Achievement: stated honestly for the operational target, per R1. The criterion fails on the coverage limb |
| R3 | Retail investors | Material risks legible | Pass | The climate section itself, not the financial-statement notes, states that Mozal Aluminium was placed on care and maintenance in March 2026 after failing to secure affordable electricity, that Hillside's electricity contract expires in 2031, that the alternative pathway was to close that smelter on expiry and that this pathway underpins long-term financial reporting assumptions, and that the announced sale would materially change the portfolio, the emissions profile and the target. Each is in plain terms on the page a retail reader reaches |
| R4 | Retail investors | Caveats findable, understandable, fairly presented | Partial | The two-basis convention is footnoted on every table, the boundaries table explains it, the absence of an interim target and of third-party validation are both stated in terms, the gross-equals-net position is stated, and the "target versus goal" distinction is footnoted. Against that, the plan-at-a-glance restates the FY35 target unqualified on the page before the sale disclosure, the 100% Transition Materials figure carries its denominator exclusions in footnotes rather than beside the number, and the renewable share halving is in the data book only. Workable: the reader's action is to read the FY35 target subsection and the methodology target table, which are consistently placed and carry every caveat; the disclosed data are that subsection and that table |
| P1 | Consumers & public | Claims literally true within their implied boundary | Pass | Every claim tested holds within the boundary its own words set. The 20.5 MtCO₂e figure and the 17.1% are arithmetically correct on the two numbers used, and the mixed basis runs against the company rather than for it. The 100% Transition Materials claim is true against the stated classification and footnoted denominator. The engagement percentages are true on the measures the company defines. The gross-equals-net statement is supported by a retirement register showing no credits applied. The 2050 position is expressly labelled a goal with no identified pathway. No carbon-neutral or net-zero-achieved claim is made |
| P2 | Consumers & public | No greenwashing or misleading composite impression | Partial | The set of accurate statements pulls in two directions and the corrections are present. A public reader meets a portfolio described as 100% Transition Materials, a target to halve emissions, engagement objectives met early, and a smelter closure attributed to circumstances outside management's control. On the same pages they also meet 17.1% above baseline, value-chain emissions up 22%, US$3.4 million of decarbonisation expenditure, and a pro-forma baseline of 1.7 MtCO₂e. What remains is placement rather than absence: the transition-materials classification and the transition-materials capital sit under climate metric headings where a reader takes them for climate outcomes, and the tier split that qualifies the 100% is in a different table. Workable: the reader's action is to read the emissions section's opening sentence and the decarbonisation expenditure line, both of which state the position plainly; the disclosed data are those two statements |
| P3 | Consumers & public | Genuine climate action evidenced | Partial | Named, deployed and sized action exists: biomass consumption at Worsley nearly doubled and is stated to contribute a 3% reduction in that operation's Scope 1, AP3XLE energy efficiency technology reached 66% of Hillside's pots from 56% with a stated electricity efficiency, a steam electrification pre-feasibility phase completed, and emissions-linked freight arrangements were extended to a third counterparty. Against that, the total spend is US$3.4 million, down 68%, one study was assessed and abandoned, no abatement project was approved for execution, and the emissions the action addresses rose. Workable: the reader's action is to identify the named projects and their stated completion percentages; the disclosed data are the AP3XLE percentage, the biomass statement and the disclosed spend |
| G1 | Regulators | Standards compliance / readiness | Pass | First mandatory period, delivered without qualification: a Directors' declaration under sections 296C and 296D, an unmodified audit opinion over Scope 1 and both Scope 2 bases, an unmodified review conclusion over governance and strategy, the paragraph 29(a)(iv) split published on both Scope 2 bases, an organisational boundaries table, quantified current financial effects referenced to financial-statement line items, an internal carbon price, cross-industry metrics with page references, and transitional reliefs applied and disclosed with the December 2025 amendments early adopted. The Australian statutory figures reconcile to the National Greenhouse and Energy Reporting register to 61 tonnes on 3.48 million. The unresolved placeholders in a statutory document are a production defect recorded as F-17, not a compliance failure |
| G2 | Regulators | Cross-source / audience consistency | Partial | The target is described identically in the statutory report, the methodology and the transition plan, which is the divergence a regulator would have tested first. What survives is internal to one document: the audited figures are the continuing-operations totals while the narrated headline, the chart and the progress statement are on total operations, and the progress statement compares a total-operations figure against a baseline adjusted on the continuing-operations convention the company's own boundaries table states. The Scope 2 movement is narrated on the market-based basis without naming it while the table beside it shows the location-based basis moving the other way. Workable: the reader's action is to use the page 105 tables, which label both bases and both portfolios, and the boundaries table, which states which basis governs which disclosure; the disclosed data are those two tables |